==[[#GENERAL|GENERAL DESCRIPTION]]==
  
−
==[[#GENERAL|GENERAL]]==
+
=== Definitions of Terms ===
 +
'''Catch Basin:''' A catch basin is a curbside opening that collects surface runoff.
  
−
The inspector’s preliminary investigation should determine if the storm sewer is correctly staked and the storm sewer is the type, size and class called for in the plans, or as allowed by specification.  The storm sewer must be accompanied by the manufacturer’s certification, tested stock reports, or other requirements as specified in the ''[http://michigan.gov/mdot/0,4616,7-151-9622_11044_11367-207980--,00.html Materials Quality Assurance Manual''].
+
'''Curb and Gutter:''' Curb and gutter is the edge of the paved roadway that collects water and is designed to drain to a catch basins, downspouts, and spillways.
  
−
All sewer pipe must be clearly marked with the following information.
+
'''Detention Pond:''' A detention pond is a temporary storage area that is engineered to control storm water. Excess storm water is collected within a detention pond during heavy rain events to help mitigate flooding and erosion downstream. A detention pond typically dries out between rain events.
  
−
* Manufacturer’s name or trademark.
+
'''Outfall:''' An outfall is the outlet where a storm sewer discharges water to a body of water or basin.
  
−
* Plant location.
+
'''Retention Pond:''' A retention pond is a permanent storage area for excess storm water runoff. Excess storm water is collected in the retention pond aiding in the control of erosion. Often, there is a weir or another filtration system within the retention pond, which is used for filtering the storm water as it travels through the pond. Retention ponds can serve as artificial wetlands for the surrounding area increasing biodiversity.
  
−
* Date of manufacture.
+
'''Runoff:''' Runoff is drainage that leaves an area as surface flow and enters a storm sewer system.
  
−
* Class of pipe.
+
'''Sedimentation:''' Sedimentation is the process of depositing soils that were eroded by the flow of water.
  
−
Other sewer pipe requirements that are type-specific follow.
+
'''Storm Sewer System:''' A storm sewer system is a network of underground pipes designed to collect and discharge water.
  
−
Circular concrete pipe with elliptical reinforcement shall have lift hole cast in the pipe which will indicate the top of the pipe as installed.  These lift holes are to be sealed with concrete plugs and waterproofed after installation.
+
'''Sump:''' A sump is the lower portion of a catch basin below the outlet pipe that is used to settle out debris and suspended material prior to storm water exiting the catch basin.  
  
−
Joints for smooth lined corrugated plastic pipe (CPE) shall be provided with homing marks to indicate correct joining of the pipe and the joint material during field installation.
+
'''Watershed:''' A watershed is an area of land that drains to a specific point.
  
−
{{top}}
+
=== General Overview ===
 +
Storm sewers are an underground infrastructure system designed to manage excess surface runoff and groundwater from roadways. These systems collect water from various sources, such as curb and gutter, drainage ditches, and underdrain pipes, by utilizing the natural slope of the land to facilitate drainage through gravity. Storm sewer systems discharge untreated water into ditches, basins, streams, or rivers.
  
−
==[[#MATERIALS|MATERIALS]]==
+
The key components of storm sewer systems include:
−
 
+
# '''Inlet:''' Inlets are typically catch basins with grates to permit water to enter into the system. The grates serve to prevent large objects from entering while facilitating the entry of water and sediment. Catch basins, which have a diameter measuring in inches, allow water to descend into the storm sewer for downstream conveyance. Some catch basins are designed with a sump below the pipe elevation, aiding in sediment settlement to prevent its entry into a body of water.
−
Some concrete storm sewer pipe does not contain reinforcement and therefore requires careful handling. Any pipe damaged in transit or by handling should be rejected by the Engineer or inspector. Storm sewer pipe will be subjected to rejection if any defects, noted in the previous section for culvert pipe, are found. In addition, non-reinforced concrete sewer pipe should be inspected for the following.
+
# '''Pipe:''' Pipe is the conduit responsible for transporting water to the outlet. Project documents specify the size and class of the pipes.
 +
# '''Outlet:''' Outlets serve as the endpoint of the storm sewer system pipe. The outlet discharges water to a body of water or basin.
  
 
{{top}}
 
{{top}}
  
−
===[[#Non-reinforced Concrete Sewer|Non-reinforced Concrete Sewer]]===
+
==[[#MATERIALS|MATERIALS]]==
  
−
* Fractures and cracks passing through the shell or socket, except that a single crack not exceeding 2 inches (50 mm) in length at either end of a pipe, or a single fracture in the socket not exceeding 3 inches (75 mm) in width around the circumference of the pipe nor 2 inches (50 mm) in length into the joint, shall not be considered cause for rejection, unless these defects exist in more than 5 percent of the entire shipment or delivery.
+
All materials must meet acceptance requirements in the <ref>[https://www.michigan.gov/mdot/Business/Construction/Materials-Source-Guide Materials Source Guide]</ref> and be listed on the Contractor-provided Material Source Lists in the project files.
  
−
* Blisters where the surface is broken or which project more than 1/8 inch (3 mm) above the surface.
+
=== Description of Materials ===
 +
The pipe material and class are noted on the plans. MDOT defines the pipe by class, which is based on the amount of cover over the pipe. Refer to <ref>[https://mdotwiki.state.mi.us/images_construction/9/95/2020-Standard-Specifications-Construction.pdf#page=222 Table 402-1 of the Standard Specifications for Construction]</ref> for acceptable pipe in each class.
 +
 +
Common storm sewer pipe materials include:
 +
* Plastic:
 +
** Smooth-lined corrugated polypropylene pipe (PPP). Grey in color.
 +
** Smooth-lined corrugated polyethylene pipe (CPE) Type S. Black in color.
 +
** Corrugated polyethylene pipe (CPE) Type C. Black in color.
 +
** Corrugated polyvinylchloride pipe (CPV). White in color.
 +
* Concrete:
 +
** Reinforced concrete pipe (RCP).
 +
** Non-reinforced concrete pipe.
 +
* Metal:
 +
** Corrugated metal pipe (CMP).
 +
** Corrugated and spiral ribbed pipe (CSP).
 +
Each pipe section, regardless of type, must be clearly marked with the following:
 +
* Pipe class and specification designation (ASTM or AASHTO).
 +
* Date of manufacture.
 +
* Name or trademark of the manufacturer.
 +
* Plant identification.
 +
The marking is either painted on the inside or scribed on outside of concrete pipes, and is painted on the outside of metal and plastic pipe.
 +
 +
To aid in the joining of pipe segments and to seal the pipe so the joints do not leak, lubricant and gaskets are used.
 +
 +
Any of these materials found with defects (cracks, fractures, exposed rebar, deformities, etc.) prior to or during installation are to be rejected and removed from the project site. Any damage caused by the Contractor’s operation to existing storm sewers that are intended to be salvaged must be removed and replaced with similar material without damage or defects at no cost to the contract.
  
−
* Defects which indicate imperfect mixing or molding.
+
==== Plastic Pipe (PPP, CPE, and CPV) ====
 +
Plastic pipe is more susceptible to shipping and storage deformation than concrete or metal pipe. Improper lifting and storage can lead to misshapen sections that are difficult to lay at a proper grade if the curve is placed vertically, and difficult to lay at a proper alignment if the curve is laid horizontally. Plastic pipe should not be deformed (out-of-round) or have blemishes in the extrusion. It should not have gouges or tears on the exterior, the interior, or the bell ends. Plastic pipes should have protective gaskets installed on the spigot ends. Gaskets should be clean and not dried out during installation.
 +
 +
==== Concrete Pipe ====
 +
Concrete pipe is precast by a manufacturer and is made of cementitious materials, aggregates, and in most cases steel reinforcement.  
  
−
* Crack sufficient to impair the strength, durability or serviceability of the pipe.
+
Concrete pipe and end sections must not be cracked or chipped, especially on the bells and spigots that are to make durable watertight joints. The concrete used must be free of segregation and honeycombing. If RCP is used, the internal reinforcement steel must not be visible on the exterior.
  
−
* Variations of more than 1/8 inch (3 mm) per lineal foot (300 mm) in alignment of pipe intended to be straight.
+
==== Metal Pipe (CMP and CSP) ====
 +
Corrugated metal pipe should not be out-of-round, exhibit deviation from a straight alignment, or have dents or bends in the metal that can create loose, poorly formed joints. Bruised or broken zinc, aluminum, or polymer coating must be repaired by the Contractor in accordance with the manufacturer’s specifications at no cost to the contract.
 +
 +
==== Bedding and Backfill ====
 +
Bedding material is comprised of granular material Class IIA, or Michigan Series 34R if undercuts are required. The material used is determined by the existing subgrade material at the bottom of the trench.  
  
−
* Failure to give a clear ringing sound when placed on end and dry-tapped with a light hammer.
+
Backfill material varies depending on what is above the storm sewer being installed and the type of pipe that is used. Typical backfill consists of granular Class II, IIAA, III, or IIIA material, suitable excavated material, or a concrete encasement. Refer to the <ref>[https://mdotjboss.state.mi.us/stdplan/getStandardPlanDocument.htm?docGuid=bb935b9c-de64-445f-bfe7-91d8e85e4f5b Standard Plan R-83 series]</ref> for details.  
−
 
 
−
* Insecure attachment of branches and spurs.
 
−
 
 
−
* The complete absence of distinct web-like markings on the external surface of the pipe made by any process in which the forms are removed immediately after the concrete has been placed. This is indicative of a deficiency of water in the concrete mix.
 
  
 
{{top}}
 
{{top}}
  
−
===[[#Storm Sewer Pipe Alternates|Storm Sewer Pipe Alternates]]===
+
==[[#EQUIPMENT|EQUIPMENT]]==
 +
The following equipment can be used for storm sewer work:
 +
* Excavator
 +
* Backhoe
 +
* Front end loader
 +
* Trench box
 +
* Occasionally, a bulldozer and a vibratory roller for aggregate compaction
 +
* Plate compactor
 +
* Ho-Pac attachment
 +
* Gas powered rammer tamping machine
 +
* Air powered pogo thumper hammer
 +
* Sand/stone box
 +
* Portable concrete mixer
 +
* Cement/mortar mixing tub
 +
* Portable generator
 +
* Electric submersible pump
 +
* Trash pump
 +
* Pipe laser with target
 +
* Transit or laser level
 +
* Leveling/grade pole
 +
* Electric impact wrench
 +
* Pipe/spud bar
 +
* Small hand tools (shovel, level, pipe “cutoff” saw, etc.)
 +
* Direct tap machine for sewer tap
  
−
When only the size and class of the storm sewer pipe is specified, the Contractor may furnish any of the alternates permitted in Table [http://mdotcf.state.mi.us/public/specbook/files/2012/402%20Storm%20Sewers.pdf 402-1] of the Standard Specifications for Construction.  Additional materials are now allowed for storm sewer pipe for use on state trunkline projects based on design life and proposed pipe use. Design life is 25 years for driveway culverts, 50 years for culverts and 70 years for sewers.
+
=== Description of Equipment ===
 +
Typically, an excavator is used to remove existing storm sewers and dig the trench for new storm sewer. A laser or other acceptable alignment device is used to install the storm sewer pipe to proper grade as it is laid in the trench by the excavator. A front-end loader or excavator is used to place backfill around the pipe to be compacted in layers by a Ho-Pac or other compaction equipment. In some cases, with a large trench, a truck will dump the backfill material directly into the trench to be graded by a bulldozer before compaction.  
  
−
When a particular type of sewer pipe material is required in lieu of the classes designated in Table [http://mdotcf.state.mi.us/public/specbook/files/2012/402%20Storm%20Sewers.pdf 402-1] of the Standard Specifications for Construction, the type and size of the sewer will be specified in the proposal or plans.  A higher strength or greater thickness of sewer pipe may be substituted for the minimum strength or minimum thickness of sewer specified.
+
=== Pictures of Equipment ===
  
 
{{top}}
 
{{top}}
  
−
===[[#Flow Velocities for Sewer|Flow Velocities for Sewer]]===
+
==[[#PRECONSTRUCTION|PRECONSTRUCTION]]==
−
 
+
Prior to the start of construction, the Inspector should perform the following:
−
The velocity of flow should be sufficient to prevent sedimentation at approximately 2 feet (0.61 m) per second.  The minimum grades that will provide the self-cleaning velocities are as follows.
+
# Inspect the pipe upon arrival to the site.
 +
#* Verify the pipe meets the requirements contained in the plans, specifications, and any addenda.
 +
#** The pipe must be accompanied by the manufacturer’s certification, tested stock reports, or other requirements as specified in the Materials Quality Assurance Procedures Manual.
 +
#** Review the cover over the top of the pipe as called for in the plans and verify against the pipe chart (Table 402-1 of the Standard Specifications for Construction) for acceptable pipe installation depth and class.
 +
#* Visually inspect the pipe for defects originating from the manufacturing process or occurring during delivery and unloading at the site (such as cracks, fractures, exposed rebar, deformities etc.). Any damaged pipe should be promptly rejected by the Engineer.
 +
#** Inspect the bell and spigot end of the pipe to ensure there are no chips or cracks that might impede a watertight joint connection.
 +
#** Inspect plastic storm sewer pipe to ensure it does not exhibit deformities that would hinder water flow.
 +
#** Using survey paint, mark any rejected pipe with an “R” to indicate rejection of the pipe. It is good practice to mark both the inside and outside of the pipe.
 +
# Verify the survey stakes are placed according to the plans and the appropriate invert elevations, rim elevations, and pipe and structure IDs are labeled on the stakes.
 +
#* Ensure proper offset stakes are placed as stakes placed in the location of the proposed sewer will be removed when excavation begins.
 +
# Verify existing underground utility markings.
 +
#* Take note of any potential utility crossings and reference the plans and profiles to ensure minimum clearances are met.
 +
# Review the plans and the Special Provision for Maintenance of Traffic. There may be restrictions or staging requirements for installation of the storm sewer. Installation restrictions are typically associated with staging requirements on a project and access to side streets and driveways.
 +
# Hold an onsite meeting with the Contractor to discuss:
 +
#* The construction method that will be used to complete the work.
 +
#* Required traffic control measures, proximity of traffic to the work area, and maintaining driveways during construction.
 +
#* Communication required if impacting residents or businesses during installation.
 +
#** Residents and businesses should be contacted if there will be disruptions to services. Coordination by the Contractor with impacted users may be required if disruption is necessary.
 +
#* Review of local ordinances.
 +
#* Disposal of excavated material and material stockpile locations. The Contractor should provide authorization letters to the Engineer noting material stockpile and disposal locations.
 +
#* Soil erosion and sedimentation control measures that will be utilized to minimize soil erosion and subsequent sedimentation.
 +
#* Methods for securing the site during work operations and at the end of each workday.  
 +
#** Including maintaining appropriate cover over the top of the pipe to minimize damage to the pipe from construction traffic.  
 +
   
 +
A review of the proposed sewer depth on the profile sheets should be compared to all known existing utilities that will be crossed, and any other proposed utilities and structures to be built, with attention paid to elevation conflicts. The size of the storm sewer must be considered. The plan invert elevation might not be in conflict, but the height of the pipe above the invert might be. Likewise, an elevation shot on “top” of an existing utility needs to consider the size of the utility below the top.  
  
 
{| class="wikitable"
 
{| class="wikitable"
 +
|+
 
|-
 
|-
−
!
+
| '''Example:'''  
−
<center>'''Diameter in. (mm)'''</center>
+
The proposed invert of a 12” concrete pipe is 100.00 at the outlet and 100.50 at the inlet.  
−
!
+
The storm sewer is 100’ long. A 6” gas main exists at the middle of the run (50’ out) with a top-of-pipe elevation of 101.50.  
−
<center>'''Storm'''</center>
 
−
!
 
−
<center>'''Sanitary'''</center>
 
−
|-
 
−
|
 
−
<center>12 (300)</center>
 
−
|
 
−
<center>.33</center>
 
−
|
 
−
<center>.17</center>
 
−
|-
 
−
|
 
−
<center>15 (375)</center>
 
−
|
 
−
<center>.25</center>
 
−
|
 
−
<center>.14</center>
 
−
|-
 
−
|
 
−
<center>18 (450)</center>
 
−
|
 
−
<center>.22</center>
 
−
|
 
−
<center>.12</center>
 
−
|-
 
−
|
 
−
<center>21 (525)</center>
 
−
|
 
−
<center>.21</center>
 
−
|
 
−
<center>.12</center>
 
−
|-
 
−
|
 
−
<center>24 (600)</center>
 
−
|
 
−
<center>.17</center>
 
−
|
 
−
<center>.10</center>
 
−
|-
 
−
|
 
−
<center>30 (750)</center>
 
−
|
 
−
<center>.15</center>
 
−
|
 
−
<center>.08</center>
 
−
|-
 
−
|
 
−
<center>36 - 42 (900-1050)</center>
 
−
|
 
−
<center>.12</center>
 
−
|
 
−
<center>.07</center>
 
−
|-
 
−
|
 
−
<center>48 (1200)</center>
 
−
|
 
−
<center>.10</center>
 
−
|
 
−
<center>.06</center>
 
−
|-
 
−
|
 
−
<center>54 - 60 (1350-1500)</center>
 
−
|
 
−
<center>.09</center>
 
−
|
 
−
<center>.05</center>
 
−
|-
 
−
|
 
−
<center>66 - 78 (1650-1950)</center>
 
−
|
 
−
<center>.08</center>
 
−
|
 
−
<center></center>
 
−
|-
 
−
|
 
−
<center>84 (2100)</center>
 
−
|
 
−
<center>.07</center>
 
−
|
 
−
<center></center>
 
−
|}
 
−
<center>'''''Table 402.02-1'''''
 
  
−
'''Minimum Grades for Self-Cleaning Velocities'''</center>
+
101.5 - 0.5’ = 101.00 at the bottom of the gas pipe.
  
−
{{top}}
+
Calculate the pipe grade using rise/run.
  
−
==[[#CONSTRUCTION|CONSTRUCTION]]==
+
0.5’ rise/100’ run = 0.005’ rise per foot.
  
 +
0.005 x 50’ = 0.25 rise to the point where the gas main crosses.
 +
 +
Invert 100.00 + 0.25 = 100.25 at 50’ out + 12” (pipe size), + 0.25 pipe thickness = 101.50 at the top of the sewer 50’ out.
  
−
===[[#Installation|Installation]]===
+
There is an elevation conflict between the proposed 12” storm sewer and the existing 6” gas main.
−
 
+
|}
−
Construction methods shall be according to the health and safety requirements in subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/104%20Control%20of%20Work.pdf 104.10] of the Standard Specifications for Construction.
 
−
 
 
−
The trench excavation should begin at the downstream end of the sewer and proceed toward the upstream end.  The trench should be excavated to the lines and grades detailed on the plans, or as established by the Engineer.  The trench width shall be at least the minimum width indicated in the Standard Plan R-83 Series, Standard Plan for Utility Trenches, or a width sufficient to provide free working space and to provide for the proper compaction of the backfill around the sewer pipe.  The bottom of the trench is to be shaped to uniformly support the pipe.
 
−
 
 
−
Where rock or hardpan is encountered, the trench should be excavated a minimum of 6 inches (150 mm) below the proposed bottom of the pipe and backfilled and compacted with Granular Material Class II.  If unstable soil conditions or obstructions other than rock are encountered, and the excavation of the sewer trench below the elevation shown on the plans is necessary, the excavation, backfill and compaction of the trench shall be directed by the Engineer.  Backfill material for undercutting due to unstable soil conditions shall be Coarse Aggregate 6A.
 
−
 
 
−
House connections, water mains, gas mains, conduits and drains, when encountered in the sewer trench, must be supported and protected across the excavation.
 
  
 
{{top}}
 
{{top}}
  
−
====[[#Watertight Joints|Watertight Joints]]====
+
==[[#CONSTRUCTION|CONSTRUCTION]]==
 +
=== Trench Excavation ===
 +
Construction of a storm sewer begins with trench excavation. Excavation may include the removal of existing storm sewer and drainage structures. These removal quantities should be recorded as called for in the specifications.
  
−
All storm sewers are to be laid true to the lines and grades given, bells or grooves upgrade, ends fully and closely jointed.  Each section shall have full, firm bearing throughout its length.  All pipe sections/joint assemblies for use in sewers shall be selected from the Qualified Products List for Watertight Sewer and Culvert Joint Systems. A field assembly diagram shall be provided to the Engineer.  All sewer pipe with diameters greater than 24 inches (600 mm) shall have the pipe joints wrapped with a non-woven geotextile fabric.  The fabric shall have a minimum width of 36 inches (900 mm) and shall be centered on the joint.
+
There are many factors that determine the safe and proper width of a pipe trench. Refer to <ref>[https://www.osha.gov/laws-regs/interlinking/standards/1926%20Subpart%20P OSHA Regulation 1926, Subpart P, Excavations]</ref>, for all applicable sloping, shoring, and soil classification safety standards for excavation. Existing soil material, groundwater elevation, utilities, trees (roots), and proximity of paved surfaces (roads, sidewalks, and curbs and gutters) and buildings may all be considered by the Contractor when deciding how the trench will be excavated.  
  
−
If circular concrete pipe with elliptical reinforcement is installed, it should be installed with lift holes on top of the pipe. The manufacturer’s marks designating the top and bottom of the pipe shall not be more than 5 degrees from the vertical plane through the longitudinal axis of the pipe.  After installation, the lift holes shall be sealed with suitable concrete plugs and waterproofed.
+
In accordance with Subpart P, soil can be classified as 3 different types:
 +
# '''Type A:''' A cohesive soil with unconfined compressive strength of 1.5 ton per square foot (tsf) or greater. Examples include clay, silty clay, sandy clay, clay loam, and in some cases silty clay loan and sandy clay loam. Cemented soils like caliche and hardpan are also considered Type A soils. However, the soil cannot be classified as Type A if one or more of the following conditions are met:
 +
#* The soil is fissured.
 +
#* The soil is subject to vibration from heavy traffic, pile driving, or similar effects.
 +
#* The soil has been previously disturbed.  
 +
#* The soil is part of a sloped, layered system where the layers dip into the excavation on a slope of 4H:1V or greater.
 +
#* The material is subject to factors that would require it to be classified as a less stable material.
 +
# '''Type B:''' A cohesive soil with unconfined compressive strength greater than 0.5 tsf but less than 1.5 tsf. Granular cohesionless soils include angular gravel (crushed rock), silt, silt loam, sandy loam, and in some cases silty clay loam and sandy clay loam. Other characteristics include:
 +
#* Previously disturbed soils except those which would otherwise be classified as Type C.
 +
#* Soil that meets the compressive strength or cementation requirements for Type A but is fissured or subject to vibration.
 +
#* Dry rock that is not stable.
 +
#* Material that is part of a sloped, layered system where the layers dip into the excavation on a slope less steep than 4H:1V, but only if the material would be otherwise classified as Type B.
 +
# '''Type C:''' A cohesive soil with an unconfined compressive strength less than 0.5 tsf. Examples include gravel, sand, and loamy sand. Other characteristics include:
 +
#* Submerged soil or soil from which water is freely seeping.
 +
#* Submerged rock that is not stable.
 +
#* Material in a sloped, layered system where the layers dip into the excavation on a slope of 4H:1V or steeper.  
  
−
Reinforced concrete elliptical pipe shall be installed with the longer axis placed horizontally, unless otherwise specified.
+
Following are various sloping requirements in accordance with OSHA regulations.  
  
−
{{top}}
+
The width of the trench should be sufficient to enable a worker to place and compact material under the pipe haunches. The <ref>[https://mdotjboss.state.mi.us/stdplan/getStandardPlanDocument.htm?docGuid=bb935b9c-de64-445f-bfe7-91d8e85e4f5b Standard Plan R-83 series]</ref> provides direction for minimum trench width as a function of the pipe size.
  
−
====[[#Utility Service Interruptions|Utility Service Interruptions]]====
+
Trench boxes and/or sheeting can be used to “steepen” the banks of a trench. By limiting the width of the trench, the Contractor can minimize excavation and backfill quantities and avoid conflicts with existing utilities, tree roots, and removal of more pavements than otherwise necessary. Some sheeting systems or cofferdams require “engineering” due to depth of material retained. Refer to <ref>[https://mdotwiki.state.mi.us/images_construction/9/95/2020-Standard-Specifications-Construction.pdf#page=371 Subsection 704.03.A of the Standard Specifications for Construction]</ref>, which describes the design for sheeting and cofferdams for retaining soil in a trench greater than 6 feet deep.
  
−
Existing live sewers and service leads shall be maintained and carefully protected during the construction of the sewers. Damaged sewer or service leads shall be repaired immediately or replaced, as directed by the Engineer. Service interruptions shall be kept to a minimum and may require coordination with the local municipality or utility company.  Water, gas, telephone and electrical wire conduits can be moved above or below the sewer being constructed.  Close liaison with the utility companies that might be in the area is particularly desirable.  It is best to have the sewer trench excavated well ahead of the laying operation to allow lead time in making any necessary modifications. Abrupt changes in grade require manholes, as do changes in alignment, change in size of sewer and junction of sewer lines.
+
The trench must be excavated and graded to the proper alignment and grade, leaving room for at least 4 inches of granular material as a bedding layer below the pipe. The bedding material must be graded uncompacted uniformly so the entire length of the pipe is firmly supported. If the pipe has bells that are larger in diameter than the barrel of the pipe, the surface of the bedding at the location of the bell can be lowered, so the bell is not propped up creating a void beneath the barrel or a misalignment of the pipe. The Contractor should not adjust the grade of the as-placed pipe in the trench with an excavator or other equipment.
  
−
If it is found necessary to flatten the sewer grade to miss unforeseen obstructions, the capacity may be affected to the extent that a larger size pipe is required. Such matters should be discussed with the Engineer, who may also confer with the designer prior to making the change, especially as it may result in extensive redesign.
+
Where rock or unyielding hardpan is encountered in the storm sewer trench, it should be excavated to a minimum of 6 inches below the proposed bottom of the pipe, backfilled with granular material Class IIIA, and compacted. The <ref>[https://mdotjboss.state.mi.us/stdplan/getStandardPlanDocument.htm?docGuid=bb935b9c-de64-445f-bfe7-91d8e85e4f5b Standard Plan R-83 series]</ref> provides details for bedding and filling around storm sewers in various applications and should be strictly followed. Backfill should be thoroughly compacted under the haunches of the pipe to provide uniform bearing throughout.  
  
−
On occasion, a utility company prefers to encase its line in a conduit and run it through a manhole rather than adjust its grade.  Be sure the manhole internal area is large enough so as not to constrict the flow. This is generally not the most desirable solution to this type of problem, as it may introduce contamination into water lines or a gas leak into the sewer system. In these situations, field decisions must be made promptly, yet with every consideration for the public’s well-being. If the facility being constructed is to eventually become the property of another agency, their concurrence should be obtained before making the changes.
+
=== Dewatering ===
 +
Dewatering of the trench may be required if either the groundwater elevation or water in the existing ditches is inundating the trench bottom. If pumps are employed to control the water, proper soil erosion and sedimentation control should be employed as well. Running the discharge of a pump through a filter bag is a common requirement. In some cases, multiple filter bags may be required. Direct discharge of pumped water to a watercourse is prohibited.  
  
−
{{top}}
+
=== Undercutting ===
 +
Undercutting the proposed trench bottom may be required if the material in the bottom is unstable and will not sufficiently support the pipe. Trench undercutting has a separate pay item (Trench Undercut and Backfill) that must be calculated by the cubic yard. Refer to <ref>[https://mdotwiki.state.mi.us/images_construction/9/95/2020-Standard-Specifications-Construction.pdf#page=229 Subsection 402.04.E of the Standard Specifications for Construction]</ref> for construction details and method of payment, respectively. The additional depth below the intended trench bottom must be backfilled with Michigan Series 6A, 17A, or 46G aggregate. Granular material (Class I, II, or III) and other “suitable material” are not acceptable and not included in the pay item.
  
−
===[[#Backfilling Sewer Pipe|Backfilling Sewer Pipe]]===
+
=== Bedding ===
 +
Storm sewer should be placed on suitable bedding material. Soft or spongy materials do not provide a firm bed for storm sewers. Excavation and bedding for storm sewers must be in accordance with <ref>[https://mdotwiki.state.mi.us/images_construction/9/95/2020-Standard-Specifications-Construction.pdf#page=212 Subsection 401.03 of the Standard Specifications for Construction]</ref>. Storm sewer bedding must be constructed uncompacted using a minimum 4-inch layer of granular Class III or IIIA material in accordance with the details in the <ref>[https://mdotjboss.state.mi.us/stdplan/getStandardPlanDocument.htm?docGuid=bb935b9c-de64-445f-bfe7-91d8e85e4f5b Standard Plan R-83 series]</ref>.
  
−
Backfilling sewer pipe will be as specified in subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/401%20Pipe%20Culverts.pdf 401.03] of the Standard Specifications for Construction and as described in this manual under culverts.
+
=== Pipe Placement ===
 +
Pipe laying typically begins at the outlet end and proceeds uphill with the bells on the higher end. Sometimes storm sewers must be laid backwards from the inlet end downhill. In this case, the pipe bells should still be laid to the higher end of the individual pipe sections.  
  
−
{{top}}
+
The first piece of pipe laid should be set to the plan invert elevation and reasonably at the plan grade. Typically, a pipe laser is used to control the alignment and the grade by directing the beam at a target placed in the pipe. The plan grade is entered into the pipe laser and the laser is directed in the plan alignment of the storm sewer by sighting the centerline of the opposite end where the target is placed, which is measured from the offset stakes. By checking the invert elevation of the first pipe with the “cut/fill” of the offset stakes and checking the invert elevation (rise/run) periodically throughout the pipe laying operation, the Inspector will know if the plan elevations are being maintained.
  
−
===[[#Sewer Pipe Jacked-in-Place|Sewer Pipe Jacked-in-Place]]===
+
The Contractor should not use a backhoe bucket or other excavation equipment to adjust the grade of the pipe. If the grade needs to be increased or decreased, the end of the pipe should be lifted to remove excess material or add additional material. Using a backhoe bucket or other excavation equipment to adjust the grade will damage the pipe.
  
−
Follow the requirements of subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/401%20Pipe%20Culverts.pdf 401.03] of the Standard Specifications for Construction and this manual under [[401 - Culverts|Section 401, Pipe Culverts Jacked-In-Place]], except that joints for pipe 36 inches (900 mm) in diameter and smaller shall be sealed with flexible watertight rubber gaskets.
+
The Inspector should verify the pipe sections are pushed home completely during installation. Ensure the Contractor does not forcefully slam the pipe connections together.  
  
−
{{top}}
+
Prior to backfilling, all pipe joints must be wrapped with a non-woven geotextile blanket. The fabric must have a minimum width of 36 inches, be centered on the joint, and overlap on the ends by at least 12 inches.
  
−
===[[#Sewer Taps|Sewer Taps]]===
+
The joints of CMP are different than the description above because there are no bells and spigots. The ends of the pipe sections are joined using couplers made of an open steel band that is passed around the joint and then secured with a bolted connection. To make the joint watertight, a gasket must be placed around the pipe between the coupler and the pipe. After the bolt(s) have been tightened on the coupler, the joint is wrapped, as described above, with geotextile blanket.
  
−
Connections to storm sewers owned by counties, municipalities or drain commissions shall be according to the regulations of the owner and according to the plans and specifications. If there is a conflict between the owner’s regulations and the Standard Specifications for Construction, the owner’s requirements will take precedence.  Connections to existing storm sewers having a plug or bulkhead shall be made with a watertight joint.  When tapping an existing pipe or structure, a minimum opening of the entering pipe’s outside diameter plus 6 inches (150 mm) shall be cut into the receiving structure.  A minimum 3 inch (75 mm) mortar layer shall be packed completely around the entering pipe and struck smooth with the inner wall of the pipe or structure. Pipe passing through the pipe or structure wall is to be cut flush to conform to the inner wall. The entering pipe on the outside portion of the connection shall be encased to provide sufficient bearing under the pipe.  Direct tapping sewers is restricted to entering pipes with outside diameters less than half the inside diameter of the trunk sewer.  All other taps will require construction of a manhole structure according to Section [http://mdotcf.state.mi.us/public/specbook/files/2012/403%20Drainage%20Structures.pdf 403] of the Standard Specifications for Construction and [[403 - Drainage Structures|Section 403, Drainage Structures]], of this manual.
+
Elliptical concrete pipe should be installed with the lift holes on the top of the pipe. The manufacturer’s marks designating the top and bottom of the pipe should not be more than 5 degrees from the vertical plane through the longitudinal axis of the pipe. After installation, the lift holes should be sealed with suitable concrete plugs and waterproofed.
 +
Flow velocities within a pipe must be sufficient to prevent sedimentation at an approximate flow of 2 feet per second (fps). The minimum pipe slopes to provide a self-cleaning velocity are detailed in the following table:
  
−
{{top}}
+
{| class="wikitable"
−
 
+
|+
−
===[[#Illicit Connections|Illicit Connections]]===
+
|-
−
 
+
! Diameter (inches) !! Storm (fps) !! Sanitary (fps)
−
If connections to MDOT's storm sewer system are found during a construction project that convey anything other than stormwater (e.g. presence of suds, oil sheen, or sewage smell) the Engineer must contact the [https://stateofmichigan.sharepoint.com/sites/mdot/Organizational/development/environmental/SitePages/IDEP%20Contacts.aspx?&originalPath=aHR0cHM6Ly9zdGF0ZW9mbWljaGlnYW4uc2hhcmVwb2ludC5jb20vOnU6L3MvbWRvdC9Pcmdhbml6YXRpb25hbC9kZXZlbG9wbWVudC9lbnZpcm9ubWVudGFsL0VYTTVTQ2tPZzNkTnIyM1lLejRYTEdjQk9GVHdVZmRFdkJKR3ltU0lKVEtiS2c_cnRpbWU9eFU5d2NLdEsyRWc Region illicit discharge elimination program (IDEP) coordinator] and follow the procedures listed in the [https://stateofmichigan.sharepoint.com/sites/mdot/Organizational/development/developmentserv/Utility%20Coordination%20%20Permits/Construction%20Permit%20Manual%20and%20Desk%20Operating%20Manual_Updated.pdf?CT=1609799746928&OR=Outlook-Body&CID=9813D456-2B15-4FC4-B95B-A9DDDCE86451 Construction Permit Manual (Section 1512.71)] for investigating and reporting.  
+
|-
−
 
+
| 12 || 0.33 || 0.17
−
If the discharge appears to be of an emergency nature, contact the Pollution Emergency Alerting System (PEAS) hotline at: (800) 292-4706
+
|-
−
 
+
| 15 || 0.25 || 0.14
−
 
+
|-
−
{{top}}
+
| 18 || 0.22 || 0.12
 +
|-
 +
| 21 || 0.21 || 0.12
 +
|-
 +
| 24 || 0.17 || 0.10
 +
|-
 +
| 30 || 0.15 || 0.08
 +
|-
 +
| 36-42 || 0.12 || 0.07
 +
|-
 +
| 48 || 0.10 || 0.06
 +
|-
 +
| 54-60 || 0.09 || 0.05
 +
|-
 +
| 66-78 || 0.08 || -
 +
|-
 +
| 84 || 0.07 || -
 +
|}
  
−
==[[#MEASUREMENT AND PAYMENT|MEASUREMENT AND PAYMENT]]==
 
−
 
−
 
−
===[[#Inspection After Installation|Inspection After Installation]]===
 
−
 
−
All of the general inspection points in the previous section on culverts apply to sewer pipes.
 
  
 
{{top}}
 
{{top}}
  
−
====[[#Mandrel Testing|Mandrel Testing]]====
 
−
 
−
Please refer to [http://mdotwiki.state.mi.us/construction/index.php/Mandrel_Testing_of_Plastic_Pipe Mandrel Testing for Plastic Pipe] for more information.
 
−
 
−
{{top}}
 
−
 
−
====[[#Video Inspection of Installed Storm Sewers|Video Inspection of Installed Storm Sewers]]====
 
−
 
−
As with culverts installed on the project, inspection by videotaping of all types of installed storm sewer is required for storm sewers with diameters from 12 to 36 inches (300 to 900 mm) with the following exceptions.
 
−
 
−
* Driveway culverts.
 
−
 
−
* Culvert extensions of less than 50 feet (15 m).
 
−
 
−
* Extension of existing catch basin leads of less than 20 feet (6 m).
 
−
 
−
* New culverts of less than 50 feet (15 m).
 
−
 
−
The purpose of the video inspection is to determine any damage or installation defects to the sewer, including pipe deformation, cracking, joint separation, corrosion, perforation, excessive siltation, excessive ponding of water, or any discernable feature observed in the video.  For corrugated plastic pipe, videotaping of all pipe 12 to 36 inches (300 to 900 mm) in diameter, unless an exception as listed above, is required after installation, regardless of whether the same pipe is mandrel tested by specification.  The sole purpose of the mandrel testing is to determine deformation.
 
−
 
−
The videotaping is to be performed by the Contractor.  For sewers installed under the pavement, the inspection shall be conducted after the required backfill compaction of the trench has been achieved, and between 5 and 10 working days prior to pavement surfacing or completion of final grade, except as otherwise approved by the Engineer.  For sewers not under pavement, the video inspection shall be conducted as close to project completion as possible, while still allowing sufficient time for corrective action determined to be necessary from the video inspection and as directed by the Engineer.  All video inspection shall be conducted as described in subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/402%20Storm%20Sewers.pdf 402.03] of the Standard Specifications for Construction.
 
−
 
−
{{top}}
 
  
 
[[Category:Construction Manual]]
 
[[Category:Construction Manual]]
 
[[Category:Division 4]]
 
[[Category:Division 4]]
 
[[Category:Section 402]]
 
[[Category:Section 402]]

Revision as of 13:56, 9 July 2025

402
Storm Sewers
2012 STANDARD SPECIFICATIONS FOR CONSTRUCTION - SECTION 402

GENERAL DESCRIPTION

Definitions of Terms

Catch Basin: A catch basin is a curbside opening that collects surface runoff.

Curb and Gutter: Curb and gutter is the edge of the paved roadway that collects water and is designed to drain to a catch basins, downspouts, and spillways.

Detention Pond: A detention pond is a temporary storage area that is engineered to control storm water. Excess storm water is collected within a detention pond during heavy rain events to help mitigate flooding and erosion downstream. A detention pond typically dries out between rain events.

Outfall: An outfall is the outlet where a storm sewer discharges water to a body of water or basin.

Retention Pond: A retention pond is a permanent storage area for excess storm water runoff. Excess storm water is collected in the retention pond aiding in the control of erosion. Often, there is a weir or another filtration system within the retention pond, which is used for filtering the storm water as it travels through the pond. Retention ponds can serve as artificial wetlands for the surrounding area increasing biodiversity.

Runoff: Runoff is drainage that leaves an area as surface flow and enters a storm sewer system.

Sedimentation: Sedimentation is the process of depositing soils that were eroded by the flow of water.

Storm Sewer System: A storm sewer system is a network of underground pipes designed to collect and discharge water.

Sump: A sump is the lower portion of a catch basin below the outlet pipe that is used to settle out debris and suspended material prior to storm water exiting the catch basin.

Watershed: A watershed is an area of land that drains to a specific point.

General Overview

Storm sewers are an underground infrastructure system designed to manage excess surface runoff and groundwater from roadways. These systems collect water from various sources, such as curb and gutter, drainage ditches, and underdrain pipes, by utilizing the natural slope of the land to facilitate drainage through gravity. Storm sewer systems discharge untreated water into ditches, basins, streams, or rivers.

The key components of storm sewer systems include:

  1. Inlet: Inlets are typically catch basins with grates to permit water to enter into the system. The grates serve to prevent large objects from entering while facilitating the entry of water and sediment. Catch basins, which have a diameter measuring in inches, allow water to descend into the storm sewer for downstream conveyance. Some catch basins are designed with a sump below the pipe elevation, aiding in sediment settlement to prevent its entry into a body of water.
  2. Pipe: Pipe is the conduit responsible for transporting water to the outlet. Project documents specify the size and class of the pipes.
  3. Outlet: Outlets serve as the endpoint of the storm sewer system pipe. The outlet discharges water to a body of water or basin.

[top of page]


MATERIALS

All materials must meet acceptance requirements in the [1] and be listed on the Contractor-provided Material Source Lists in the project files.

Description of Materials

The pipe material and class are noted on the plans. MDOT defines the pipe by class, which is based on the amount of cover over the pipe. Refer to [2] for acceptable pipe in each class.

Common storm sewer pipe materials include:

  • Plastic:
    • Smooth-lined corrugated polypropylene pipe (PPP). Grey in color.
    • Smooth-lined corrugated polyethylene pipe (CPE) Type S. Black in color.
    • Corrugated polyethylene pipe (CPE) Type C. Black in color.
    • Corrugated polyvinylchloride pipe (CPV). White in color.
  • Concrete:
    • Reinforced concrete pipe (RCP).
    • Non-reinforced concrete pipe.
  • Metal:
    • Corrugated metal pipe (CMP).
    • Corrugated and spiral ribbed pipe (CSP).

Each pipe section, regardless of type, must be clearly marked with the following:

  • Pipe class and specification designation (ASTM or AASHTO).
  • Date of manufacture.
  • Name or trademark of the manufacturer.
  • Plant identification.

The marking is either painted on the inside or scribed on outside of concrete pipes, and is painted on the outside of metal and plastic pipe.

To aid in the joining of pipe segments and to seal the pipe so the joints do not leak, lubricant and gaskets are used.

Any of these materials found with defects (cracks, fractures, exposed rebar, deformities, etc.) prior to or during installation are to be rejected and removed from the project site. Any damage caused by the Contractor’s operation to existing storm sewers that are intended to be salvaged must be removed and replaced with similar material without damage or defects at no cost to the contract.

Plastic Pipe (PPP, CPE, and CPV)

Plastic pipe is more susceptible to shipping and storage deformation than concrete or metal pipe. Improper lifting and storage can lead to misshapen sections that are difficult to lay at a proper grade if the curve is placed vertically, and difficult to lay at a proper alignment if the curve is laid horizontally. Plastic pipe should not be deformed (out-of-round) or have blemishes in the extrusion. It should not have gouges or tears on the exterior, the interior, or the bell ends. Plastic pipes should have protective gaskets installed on the spigot ends. Gaskets should be clean and not dried out during installation.

Concrete Pipe

Concrete pipe is precast by a manufacturer and is made of cementitious materials, aggregates, and in most cases steel reinforcement.

Concrete pipe and end sections must not be cracked or chipped, especially on the bells and spigots that are to make durable watertight joints. The concrete used must be free of segregation and honeycombing. If RCP is used, the internal reinforcement steel must not be visible on the exterior.

Metal Pipe (CMP and CSP)

Corrugated metal pipe should not be out-of-round, exhibit deviation from a straight alignment, or have dents or bends in the metal that can create loose, poorly formed joints. Bruised or broken zinc, aluminum, or polymer coating must be repaired by the Contractor in accordance with the manufacturer’s specifications at no cost to the contract.

Bedding and Backfill

Bedding material is comprised of granular material Class IIA, or Michigan Series 34R if undercuts are required. The material used is determined by the existing subgrade material at the bottom of the trench.

Backfill material varies depending on what is above the storm sewer being installed and the type of pipe that is used. Typical backfill consists of granular Class II, IIAA, III, or IIIA material, suitable excavated material, or a concrete encasement. Refer to the [3] for details.

[top of page]


EQUIPMENT

The following equipment can be used for storm sewer work:

  • Excavator
  • Backhoe
  • Front end loader
  • Trench box
  • Occasionally, a bulldozer and a vibratory roller for aggregate compaction
  • Plate compactor
  • Ho-Pac attachment
  • Gas powered rammer tamping machine
  • Air powered pogo thumper hammer
  • Sand/stone box
  • Portable concrete mixer
  • Cement/mortar mixing tub
  • Portable generator
  • Electric submersible pump
  • Trash pump
  • Pipe laser with target
  • Transit or laser level
  • Leveling/grade pole
  • Electric impact wrench
  • Pipe/spud bar
  • Small hand tools (shovel, level, pipe “cutoff” saw, etc.)
  • Direct tap machine for sewer tap

Description of Equipment

Typically, an excavator is used to remove existing storm sewers and dig the trench for new storm sewer. A laser or other acceptable alignment device is used to install the storm sewer pipe to proper grade as it is laid in the trench by the excavator. A front-end loader or excavator is used to place backfill around the pipe to be compacted in layers by a Ho-Pac or other compaction equipment. In some cases, with a large trench, a truck will dump the backfill material directly into the trench to be graded by a bulldozer before compaction.

Pictures of Equipment

[top of page]


PRECONSTRUCTION

Prior to the start of construction, the Inspector should perform the following:

  1. Inspect the pipe upon arrival to the site.
    • Verify the pipe meets the requirements contained in the plans, specifications, and any addenda.
      • The pipe must be accompanied by the manufacturer’s certification, tested stock reports, or other requirements as specified in the Materials Quality Assurance Procedures Manual.
      • Review the cover over the top of the pipe as called for in the plans and verify against the pipe chart (Table 402-1 of the Standard Specifications for Construction) for acceptable pipe installation depth and class.
    • Visually inspect the pipe for defects originating from the manufacturing process or occurring during delivery and unloading at the site (such as cracks, fractures, exposed rebar, deformities etc.). Any damaged pipe should be promptly rejected by the Engineer.
      • Inspect the bell and spigot end of the pipe to ensure there are no chips or cracks that might impede a watertight joint connection.
      • Inspect plastic storm sewer pipe to ensure it does not exhibit deformities that would hinder water flow.
      • Using survey paint, mark any rejected pipe with an “R” to indicate rejection of the pipe. It is good practice to mark both the inside and outside of the pipe.
  2. Verify the survey stakes are placed according to the plans and the appropriate invert elevations, rim elevations, and pipe and structure IDs are labeled on the stakes.
    • Ensure proper offset stakes are placed as stakes placed in the location of the proposed sewer will be removed when excavation begins.
  3. Verify existing underground utility markings.
    • Take note of any potential utility crossings and reference the plans and profiles to ensure minimum clearances are met.
  4. Review the plans and the Special Provision for Maintenance of Traffic. There may be restrictions or staging requirements for installation of the storm sewer. Installation restrictions are typically associated with staging requirements on a project and access to side streets and driveways.
  5. Hold an onsite meeting with the Contractor to discuss:
    • The construction method that will be used to complete the work.
    • Required traffic control measures, proximity of traffic to the work area, and maintaining driveways during construction.
    • Communication required if impacting residents or businesses during installation.
      • Residents and businesses should be contacted if there will be disruptions to services. Coordination by the Contractor with impacted users may be required if disruption is necessary.
    • Review of local ordinances.
    • Disposal of excavated material and material stockpile locations. The Contractor should provide authorization letters to the Engineer noting material stockpile and disposal locations.
    • Soil erosion and sedimentation control measures that will be utilized to minimize soil erosion and subsequent sedimentation.
    • Methods for securing the site during work operations and at the end of each workday.
      • Including maintaining appropriate cover over the top of the pipe to minimize damage to the pipe from construction traffic.

A review of the proposed sewer depth on the profile sheets should be compared to all known existing utilities that will be crossed, and any other proposed utilities and structures to be built, with attention paid to elevation conflicts. The size of the storm sewer must be considered. The plan invert elevation might not be in conflict, but the height of the pipe above the invert might be. Likewise, an elevation shot on “top” of an existing utility needs to consider the size of the utility below the top.

Example:

The proposed invert of a 12” concrete pipe is 100.00 at the outlet and 100.50 at the inlet. The storm sewer is 100’ long. A 6” gas main exists at the middle of the run (50’ out) with a top-of-pipe elevation of 101.50.

101.5 - 0.5’ = 101.00 at the bottom of the gas pipe.

Calculate the pipe grade using rise/run.

0.5’ rise/100’ run = 0.005’ rise per foot.

0.005 x 50’ = 0.25 rise to the point where the gas main crosses.

Invert 100.00 + 0.25 = 100.25 at 50’ out + 12” (pipe size), + 0.25 pipe thickness = 101.50 at the top of the sewer 50’ out.

There is an elevation conflict between the proposed 12” storm sewer and the existing 6” gas main.

[top of page]


CONSTRUCTION

Trench Excavation

Construction of a storm sewer begins with trench excavation. Excavation may include the removal of existing storm sewer and drainage structures. These removal quantities should be recorded as called for in the specifications.

There are many factors that determine the safe and proper width of a pipe trench. Refer to [4], for all applicable sloping, shoring, and soil classification safety standards for excavation. Existing soil material, groundwater elevation, utilities, trees (roots), and proximity of paved surfaces (roads, sidewalks, and curbs and gutters) and buildings may all be considered by the Contractor when deciding how the trench will be excavated.

In accordance with Subpart P, soil can be classified as 3 different types:

  1. Type A: A cohesive soil with unconfined compressive strength of 1.5 ton per square foot (tsf) or greater. Examples include clay, silty clay, sandy clay, clay loam, and in some cases silty clay loan and sandy clay loam. Cemented soils like caliche and hardpan are also considered Type A soils. However, the soil cannot be classified as Type A if one or more of the following conditions are met:
    • The soil is fissured.
    • The soil is subject to vibration from heavy traffic, pile driving, or similar effects.
    • The soil has been previously disturbed.
    • The soil is part of a sloped, layered system where the layers dip into the excavation on a slope of 4H:1V or greater.
    • The material is subject to factors that would require it to be classified as a less stable material.
  2. Type B: A cohesive soil with unconfined compressive strength greater than 0.5 tsf but less than 1.5 tsf. Granular cohesionless soils include angular gravel (crushed rock), silt, silt loam, sandy loam, and in some cases silty clay loam and sandy clay loam. Other characteristics include:
    • Previously disturbed soils except those which would otherwise be classified as Type C.
    • Soil that meets the compressive strength or cementation requirements for Type A but is fissured or subject to vibration.
    • Dry rock that is not stable.
    • Material that is part of a sloped, layered system where the layers dip into the excavation on a slope less steep than 4H:1V, but only if the material would be otherwise classified as Type B.
  3. Type C: A cohesive soil with an unconfined compressive strength less than 0.5 tsf. Examples include gravel, sand, and loamy sand. Other characteristics include:
    • Submerged soil or soil from which water is freely seeping.
    • Submerged rock that is not stable.
    • Material in a sloped, layered system where the layers dip into the excavation on a slope of 4H:1V or steeper.

Following are various sloping requirements in accordance with OSHA regulations.

The width of the trench should be sufficient to enable a worker to place and compact material under the pipe haunches. The [5] provides direction for minimum trench width as a function of the pipe size.

Trench boxes and/or sheeting can be used to “steepen” the banks of a trench. By limiting the width of the trench, the Contractor can minimize excavation and backfill quantities and avoid conflicts with existing utilities, tree roots, and removal of more pavements than otherwise necessary. Some sheeting systems or cofferdams require “engineering” due to depth of material retained. Refer to [6], which describes the design for sheeting and cofferdams for retaining soil in a trench greater than 6 feet deep.

The trench must be excavated and graded to the proper alignment and grade, leaving room for at least 4 inches of granular material as a bedding layer below the pipe. The bedding material must be graded uncompacted uniformly so the entire length of the pipe is firmly supported. If the pipe has bells that are larger in diameter than the barrel of the pipe, the surface of the bedding at the location of the bell can be lowered, so the bell is not propped up creating a void beneath the barrel or a misalignment of the pipe. The Contractor should not adjust the grade of the as-placed pipe in the trench with an excavator or other equipment.

Where rock or unyielding hardpan is encountered in the storm sewer trench, it should be excavated to a minimum of 6 inches below the proposed bottom of the pipe, backfilled with granular material Class IIIA, and compacted. The [7] provides details for bedding and filling around storm sewers in various applications and should be strictly followed. Backfill should be thoroughly compacted under the haunches of the pipe to provide uniform bearing throughout.

Dewatering

Dewatering of the trench may be required if either the groundwater elevation or water in the existing ditches is inundating the trench bottom. If pumps are employed to control the water, proper soil erosion and sedimentation control should be employed as well. Running the discharge of a pump through a filter bag is a common requirement. In some cases, multiple filter bags may be required. Direct discharge of pumped water to a watercourse is prohibited.

Undercutting

Undercutting the proposed trench bottom may be required if the material in the bottom is unstable and will not sufficiently support the pipe. Trench undercutting has a separate pay item (Trench Undercut and Backfill) that must be calculated by the cubic yard. Refer to [8] for construction details and method of payment, respectively. The additional depth below the intended trench bottom must be backfilled with Michigan Series 6A, 17A, or 46G aggregate. Granular material (Class I, II, or III) and other “suitable material” are not acceptable and not included in the pay item.

Bedding

Storm sewer should be placed on suitable bedding material. Soft or spongy materials do not provide a firm bed for storm sewers. Excavation and bedding for storm sewers must be in accordance with [9]. Storm sewer bedding must be constructed uncompacted using a minimum 4-inch layer of granular Class III or IIIA material in accordance with the details in the [10].

Pipe Placement

Pipe laying typically begins at the outlet end and proceeds uphill with the bells on the higher end. Sometimes storm sewers must be laid backwards from the inlet end downhill. In this case, the pipe bells should still be laid to the higher end of the individual pipe sections.

The first piece of pipe laid should be set to the plan invert elevation and reasonably at the plan grade. Typically, a pipe laser is used to control the alignment and the grade by directing the beam at a target placed in the pipe. The plan grade is entered into the pipe laser and the laser is directed in the plan alignment of the storm sewer by sighting the centerline of the opposite end where the target is placed, which is measured from the offset stakes. By checking the invert elevation of the first pipe with the “cut/fill” of the offset stakes and checking the invert elevation (rise/run) periodically throughout the pipe laying operation, the Inspector will know if the plan elevations are being maintained.

The Contractor should not use a backhoe bucket or other excavation equipment to adjust the grade of the pipe. If the grade needs to be increased or decreased, the end of the pipe should be lifted to remove excess material or add additional material. Using a backhoe bucket or other excavation equipment to adjust the grade will damage the pipe.

The Inspector should verify the pipe sections are pushed home completely during installation. Ensure the Contractor does not forcefully slam the pipe connections together.

Prior to backfilling, all pipe joints must be wrapped with a non-woven geotextile blanket. The fabric must have a minimum width of 36 inches, be centered on the joint, and overlap on the ends by at least 12 inches.

The joints of CMP are different than the description above because there are no bells and spigots. The ends of the pipe sections are joined using couplers made of an open steel band that is passed around the joint and then secured with a bolted connection. To make the joint watertight, a gasket must be placed around the pipe between the coupler and the pipe. After the bolt(s) have been tightened on the coupler, the joint is wrapped, as described above, with geotextile blanket.

Elliptical concrete pipe should be installed with the lift holes on the top of the pipe. The manufacturer’s marks designating the top and bottom of the pipe should not be more than 5 degrees from the vertical plane through the longitudinal axis of the pipe. After installation, the lift holes should be sealed with suitable concrete plugs and waterproofed. Flow velocities within a pipe must be sufficient to prevent sedimentation at an approximate flow of 2 feet per second (fps). The minimum pipe slopes to provide a self-cleaning velocity are detailed in the following table:

Diameter (inches) Storm (fps) Sanitary (fps)
12 0.33 0.17
15 0.25 0.14
18 0.22 0.12
21 0.21 0.12
24 0.17 0.10
30 0.15 0.08
36-42 0.12 0.07
48 0.10 0.06
54-60 0.09 0.05
66-78 0.08 -
84 0.07 -