2.08 Performance Assessment Plan (PAP)
(Updated 12/3/2020)
Once the project is under construction, the PAP includes documentation of traffic delays, travel times, queues, volumes, and associated information. The information will assist in the verification of data and if additional measures must be taken to amend the TMP. Traffic incidents (crashes, load spills, natural disasters, etc.) should be documented and analyzed to determine if work zone hazards have developed that require action.
The TSC Traffic & Safety Operations Engineer should be made aware of all traffic incidents in the work zone
Work zone safety and mobility should be monitored, measured, and documented during the construction phase of each significant project to verify the mitigation measures and strategies are performing as expected, as stated in the TMP. The TMP will be used as the basis for the project specific PAP.