Progress Payment Estimate
| Progress Payment Estimate |
Approval level |
Role |
System Name
|
| Progress Aero State |
1 |
Aero Office Tech |
MDOT_AEROOFFICETECH
|
|
2 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Progress Aero No OT |
1 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
2 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Progress Aero Consl |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
Aero Engineer |
MDOT_AEROENGR
|
|
4 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Progress Consl Local |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
Local Project Engineer or Local Agency Representative |
LOC_PROJENGRREP
|
|
4 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Progress Consl |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
4 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Progress IBA Consl |
1 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
2 |
IBA Construction Engineer |
IBA_CONSTRENGR
|
| Progress Local |
1 |
Local Office Tech |
LOC_OFFICETECH
|
|
2 |
Local Project Engineer or Local Agency Representative |
LOC_PROJENGRREP
|
|
3 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Progress MBA |
1 |
MDOT Office Tech |
MDOT_OFFICETECH
|
|
2 |
MBA Construction Engineer |
MBA_CONSTRENGR
|
| Progress MBA Consl |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
MBA Construction Engineer |
MBA_CONSTRENGR
|
| Progress MDOT |
1 |
MDOT Tech |
MDOT_OFFICETECH
|
|
2 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
3 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Progress Rail |
1 |
MDOT Rail Project Manager EML 14 |
MDOT_RAILPROJMANEML14
|
|
2 |
MDOT Rail Managing Office Manager EML 15 |
MDOT_RAILMOMANEML15
|
|
3 |
MDOT Financial Admin |
MDOT_FINADMIN
|
Final Payment Estimate
| Final Payment Estimate |
Approval level |
Role |
System Name
|
| Final Aero State |
1 |
Aero Office Tech |
MDOT_AEROOFFICETECH
|
|
2 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Final Aero No OT |
1 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
2 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Final Aero Consl |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
Aero Engineer |
MDOT_AEROENGR
|
|
4 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Final Consl Local |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
Local Project Engineer or Local Agency Representative |
LOC_PROJENGRREP
|
|
4 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
5 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Final Consl |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
4 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Final IBA Consl |
1 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
2 |
IBA Construction Engineer |
IBA_CONSTRENGR
|
| Final Local |
1 |
Local Office Tech |
LOC_OFFICETECH
|
|
2 |
Local Project Engineer or Local Agency Representative |
LOC_PROJENGRREP
|
|
3 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
4 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Final MBA |
1 |
MDOT Office Tech |
MDOT_OFFICETECH
|
|
2 |
MBA Construction Engineer |
MBA_CONSTRENGR
|
| Final MBA Consl |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
MBA Construction Engineer |
MBA_CONSTRENGR
|
| Final MDOT |
1 |
MDOT Tech |
MDOT_OFFICETECH
|
|
2 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
3 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Final Rail |
1 |
MDOT Rail Project Manager EML 14 |
MDOT_RAILPROJMANEML14
|
|
2 |
MDOT Rail Managing Office Manager EML 15 |
MDOT_RAILMOMANEML15
|
|
3 |
MDOT Financial Admin |
MDOT_FINADMIN
|
Supplemental Payment Estimate
| Supplemental Payment Estimate |
Approval level |
Role |
System Name
|
| Suppl Aero State |
1 |
Aero Office Tech |
MDOT_AEROOFFICETECH
|
|
2 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Suppl Aero No OT |
1 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
2 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Suppl Aero Consl |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
Aero Engineer |
MDOT_AEROENGR
|
|
4 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Suppl Consl Local |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
Local Project Engineer or Local Agency Representative |
LOC_PROJENGRREP
|
|
4 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
5 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Suppl Consl |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
4 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Suppl IBA Consl |
1 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
2 |
IBA Construction Engineer |
IBA_CONSTRENGR
|
| Suppl Local |
1 |
Local Office Tech |
LOC_OFFICETECH
|
|
2 |
Local Project Engineer or Local Agency Representative |
LOC_PROJENGRREP
|
|
3 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
4 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Suppl MBA |
1 |
MDOT Office Tech |
MDOT_OFFICETECH
|
|
2 |
MBA Construction Engineer |
MBA_CONSTRENGR
|
| Suppl MBA Consl |
1 |
Consultant Office Tech |
CONSL_OFFICETECH
|
|
2 |
Consultant Project Engineer |
CONSL_PROJENGR
|
|
3 |
MBA Construction Engineer |
MBA_CONSTRENGR
|
| Suppl MDOT |
1 |
MDOT Tech |
MDOT_OFFICETECH
|
|
2 |
MDOT Construction Engineer |
MDOT_CONSTRENGR
|
|
3 |
MDOT Financial Admin |
MDOT_FINADMIN
|
| Suppl Rail |
1 |
MDOT Rail Project Manager EML 14 |
MDOT_RAILPROJMANEML14
|
|
2 |
MDOT Rail Managing Office Manager EML 15 |
MDOT_RAILMOMANEML15
|
|
3 |
MDOT Financial Admin |
MDOT_FINADMIN
|