Table 3-1 Base Mainline Capacity and Table 3-2 Capacity Adjustment Factors should be used to estimate the capacity for each open lane. Apply factors known to adjust the base work zone capacity. | Table 3-1 Base Mainline Capacity and Table 3-2 Capacity Adjustment Factors should be used to estimate the capacity for each open lane. Apply factors known to adjust the base work zone capacity. | ||
| − | To begin the development of traffic control options, determine the number of lanes needed to handle the expected demand. An early check of available roadway capacity is critical as the vast majority of additional delay due to a work zone occurs when demand exceeds capacity for any appreciable length of time. The Highway Capacity Manual (HCM) Equation 10-9 can be used to determine the resulting adjusted capacity of the roadway lane: | + | To begin the development of traffic control options, determine the number of lanes needed to handle the expected demand. An early check of available roadway capacity is critical as the vast majority of additional delay due to a work zone occurs when demand exceeds capacity for any appreciable length of time. The Highway Capacity Manual (HCM) Equation 10-9 can be used to determine the resulting adjusted capacity of the roadway lane: <div style="text-align: center;"></br> |
| − | '''''C<sub>a</sub> = {[(C<sub>b</sub> + I<sub>g</sub> + I<sub>wt</sub> + I<sub>wa</sub> ) × f<sub>hv</sub> × f<sub>lw</sub> × f<sub>sc</sub> ] × N} − R ''''' | + | <big>'''''C<sub>a</sub> = {[(C<sub>b</sub> + I<sub>g</sub> + I<sub>wt</sub> + I<sub>wa</sub> ) × f<sub>hv</sub> × f<sub>lw</sub> × f<sub>sc</sub> ] × N} − R '''''</big></div></br> |
Where: | Where: | ||
| Line 45: | Line 45: | ||
The base mainline capacity ('''''C<sub>b</sub>''''') and work zone capacity adjustment factors are provided in the tables below. | The base mainline capacity ('''''C<sub>b</sub>''''') and work zone capacity adjustment factors are provided in the tables below. | ||
| − | + | ====Table 3-1: Base Mainline Capacity==== | |
<div style="text-align: center;"> | <div style="text-align: center;"> | ||
{| class="wikitable" | {| class="wikitable" | ||
| Line 68: | Line 68: | ||
</div> | </div> | ||
| − | + | ====Table 3-2: Capacity Adjustment Factors==== | |
<div style="text-align: center;"> | <div style="text-align: center;"> | ||
{| class="wikitable" | {| class="wikitable" | ||
| Line 130: | Line 130: | ||
|} | |} | ||
</div> | </div> | ||
| + | |||
| + | =====Example 3.1: Freeway===== | ||
| + | A construction project is planned for a two-lane freeway portion of US-127. The project will last for several months and involves complete reconstruction of the roadway and several bridges on each bound. One lane of traffic is proposed to be maintained in each direction by using temporary crossovers. Maintained traffic must drive on the shoulder. Lane widths will be reduced to 11 feet, with temporary concrete barrier separating opposing traffic. The traffic characteristics consist of 7% trucks. Calculate Lane capacity. | ||
| + | |||
| + | =====Solution 3.1: Freeway===== | ||
| + | The lane capacity is computed by starting with the base capacity ('''''C<sub>b</sub>''''') for a 2 lane freeway to a 1 lane freeway 1550 vphpl. The adjustment factor applied for geometry includes use of a crossover, with a > 3 foot shift, and traffic driving on the shoulder. Since we are only allowed to use one factor '''''I<sub>g</sub>''''' = -100 (could range from 100 to 150). Although the work type is reconstruction, it is not in close proximity to the maintained traffic since it occurs on the closed bound of the freeway ('''''I<sub>wt</sub>''''' = 100). The adjustment factors applied for work activity ('''''I<sub>wa</sub>''''' = 50), lane width ('''''f<sub>lw</sub>''''' = 0.95), side clearance ('''''f<sub>sc</sub>''''' = 0.95), and percent trucks ('''''f<sub>hv</sub>''''' = 0.98). The adjusted capacity is: <div style="text-align: center;"></br> | ||
| + | <big>'''''C<sub>a</sub> = [(1550 − 100 + 100 + 50) × 0.95 × 0.95 × 0.98] = 1415 vph'''''</big></div> | ||
| + | |||
| + | =====Example 3.2: Freeway===== | ||
| + | A construction project is planned for an urban three lane freeway portion of I-696. The project will last a few months and involves replacement of median barrier and lighting fixtures. The median lane will be closed in each direction during some parts of the day using channelizing devices. The work activity is less than 12 feet from traffic. The traffic characteristics consist of 15% trucks. Calculate lane capacity. | ||
| + | |||
| + | =====Solution 3.2: Freeway===== | ||
| + | The lane capacity is computed by starting with the base capacity ('''''C<sub>b</sub>''''') for a 3 lane freeway to a 2 lane freeway 1700 vphpl. Adjustments are applied for close proximity intense work activity ('''''I<sub>g</sub>''''' = -100), ('''''I<sub>wt</sub>''''' = 50), ('''''I<sub>wa</sub>''''' = -150), side clearance ('''''f<sub>sc</sub>''''' = 0.95), percentage trucks ('''''f<sub>hv</sub>''''' = 0.95). The adjusted capacity for two open lanes is: <div style="text-align: center;"></br> | ||
| + | <big>'''''C<sub>a</sub> = {[(1700 − 100 + 50 − 100) × 0.95 × 0.95] × 2} = 2798 vph or 1399 vphpl'''''</big></div> | ||
| + | |||
| + | ===B. Traffic Demand Determination=== | ||
| + | An estimation of the hourly traffic demand is necessary to proceed with travel time delay and queue estimations. Existing traffic volume data is regularly collected on most state trunklines. Information regarding traffic data is provided in [[Work Zone - 2.03 Traffic Operations Plan (TOP)#A. Traffic Information|Section 2.03.01.A Traffic Information]]. | ||
| + | |||
| + | The level of detail of traffic volume data depends on the level of analysis. Hourly traffic volume data is necessary to accurately evaluate mobility impacts on facilities that may have fluctuations in traffic demand throughout the day. This is of particular importance if the temporary traffic control plan considers implementing traffic restrictions or lane closures only during certain portions of the day. | ||
| + | |||
| + | Weekend and weekday volumes are necessary when determining week day restrictions. Reviewing traffic volumes from the same time frame is important to make sure the traffic patterns are similar. This is amplified when dealing with an area that has a yearly traffic generator such as a school or seasonal traffic. | ||
| + | |||
| + | ===C. Speed Delay=== | ||
| + | The speed delay component of travel time delay is affected by the temporary speed limit and by the capacity conditions of the work zone. As a base line, the initial travel time (before construction work) should be computed or measured. Most roadways that operate at less than capacity, the initial travel time may be estimated by dividing the segment length by the existing posted speed limit. It should be recognized, however, in areas where recurring congestion is present, the existing travel time should be inclusive of recurring congestion due to near or at capacity operations. | ||
| + | |||
| + | Measured operating speed may be available on [https://www.ritis.org/login?r=Lw== RITIS]. Existing travel time runs should be completed to verify the existing conditions. | ||
| + | |||
| + | The proposed posted temporary speed limit should be considered the maximum operating speed during construction activities. It is important to consider the presence of special reduced speed limits in Michigan, such as the “45 MPH Where Workers Present” condition. The actual operating speed within a work zone may still be less than the posted work zone speed depending on the capacity conditions and worker location. | ||
| + | |||
| + | The relative nearness of the traffic demand to capacity is related using the V /C ratio. The V/C ratio may be used as a performance measure for the work zone operations. | ||
| + | |||
| + | The speed delay attributable to the work zone can be computed as the difference in the travel time during construction and before construction. The following formula may be used to compute speed delay:<div style="text-align: center;"></br> | ||
| + | <big>'''''t = D × ( <sup>1</sup>∕<sub>U<sub>wz</sub></sub> − <sup>1</sup>∕<sub>U<sub>i</sub></sub> ) × 60'''''</big></div></br> | ||
| + | Where: | ||
| + | </br> | ||
| + | '''''t''''' = speed delay (min) | ||
| + | </br> | ||
| + | '''''D''''' = work zone length, from reduce speed signing to return to existing roadway speed (miles) | ||
| + | </br> | ||
| + | '''''U<sub>wz</sub>''''' = operating work zone speed (mph) | ||
| + | </br> | ||
| + | '''''U<sub>i</sub>''''' = existing posted or operating speed before construction (mph) | ||
| + | |||
| + | ===D. Queue Delay=== | ||
| + | A queue is an accumulation of vehicles for each time period in which the arrivals, or demand, exceeds the departures, or capacity. The queue delay component of travel delay is estimated only when the demand exceeds capacity and a queue forms. When the demand traveling through the work zone is less than or equal to capacity, no queue is formed and no queue delay is encountered. | ||
| + | |||
| + | Spreadsheet tools or software are helpful in performing the computation of queue delay, since the accumulation and dissipation of queues may occur across multiple time periods. The delay encountered at a queue is estimated using the volume of vehicles accumulated in the queue and the capacity at which the queue is serviced. | ||
| + | |||
| + | The following formula can be used to compute the delay time for a vehicle at the back of the queue: <div style="text-align: center;"></br> | ||
| + | <big>'''''t = ( <sup>Q</sup>∕<sub>C<sub>a</sub></sub> ) × 60'''''</big></div></br> | ||
| + | Where: | ||
| + | </br> | ||
| + | '''''t''''' = queue delay (min) | ||
| + | </br> | ||
| + | '''''Q''''' = number of vehicles in queue (# of veh) | ||
| + | </br> | ||
| + | '''''C<sub>a</sub>''''' = adjusted mainline capacity (vph) | ||
| + | |||
| + | =====Example 3.3: Urban Freeway, Queue Delay===== | ||
| + | Building from Example 3.2, the demand on this urban freeway is 3000 vph. The work zone is 5 miles long and the existing posted speed is 70 mph. During Construction the work zone will be signed for: | ||
| + | <div style="text-align: center;"> | ||
| + | 45 MPH | ||
| + | Where Workers Present.</br></div> | ||
| + | Calculate the queue delay. | ||
| + | |||
| + | =====Solution 3.3 Urban Freeway, Queue Delay===== | ||
| + | The adjusted mainline capacity estimated earlier is 2798 vph. The accumulated queue for the time period (hour) is the demand that exceeds the capacity.</br> <div style="text-align: center;"> | ||
| + | <big>'''''Q = 3000 − 2798 = 202 veh''''' </big></div></br> | ||
| + | The queue delay is:</br> <div style="text-align: center;"> | ||
| + | <big>'''''t = <sup>202</sup>∕<sub>2798</sub> × 60 = 4.33 min''''' </big></div></br> | ||
| + | |||
| + | ====Table 33: Per Lane Capacity for Signalized Flow==== | ||
| + | <div style="text-align: center;"> | ||
| + | {| class="wikitable" | ||
| + | |+ Assumptions for Table 3-3: 5% trucks, level terrain, urban area </br> *Assumes no left turns through opposing traffic from lane analyzed. Left turns with opposing traffic merit special consideration. If no opposing traffic exists, left turns are treated as right turns. For example: no opposing traffic, 30% rights & 20% lefts, use table values for 50% turns. | ||
| + | |- | ||
| + | ! Colspan="3" | Lane Characteristics !! Colspan="2" | No Turns !! Colspan="2" | 50% Turns* !! Colspan="2" | 100% Turns* or </br> Right-turn lane !! U-turn crossover | ||
| + | |- | ||
| + | ! Colspan="3" | Lane width (ft) !! 12 !! 10 !! 12 !! 10 !! 12 !! 10 !! N/A | ||
| + | |- | ||
| + | | Rowspan="6" | Green Time || Rowspan="2" | 40% || Unrestricted || 620 || 550 || 560 || 500 || 520 || 450 || 530 | ||
| + | |- | ||
| + | | Restricted || 580 || 510 || 520 || 460 || 480 || 420 || 490 | ||
| + | |- | ||
| + | | Rowspan="2" | 50% || Unrestricted || 850 || 750 || 770 || 680 || 710 || 620 || 670 | ||
| + | |- | ||
| + | | Restricted || 800 || 700 || 730 || 640 || 670 || 590 || 630 | ||
| + | |- | ||
| + | | Rowspan="2" | 60% || Unrestricted || 1040 || 910 || 940 || 830 || 870 || 760 || 810 | ||
| + | |- | ||
| + | | Restricted || 970 || 850 || 880 || 780 || 810 || 710 || 760 | ||
| + | |} </div> | ||
| + | |||
| + | ==3.01.02 Traffic Regulator Operation== | ||
| + | (Updated 12/3/2020) | ||
| + | Traffic regulator operations, on the mainline traffic with alternating flow, should be evaluated based on travel time delay. The travel time delay calculation is determined using the Construction, Congestion, Cost Software [https://www.michigan.gov/mdot/Business/Construction/co-analysis (CO3) Flag Spreadsheet]. The capacity of a traffic regulator operation is directly related to the posted work zone speed, volume of traffic, and the length of the traffic regulator zone. | ||
| + | |||
| + | The chart and graphs provided in Appendix B: Mobility Analysis Tools present capacity during traffic regulating on two-lane roadways. Once this determination is made, it can be used in the CO3 analysis to evaluate the travel time delay associated with work zone lengths. The value, as determined by the chart and the CO3 analysis, should be specified in the TMP. The length of the work zone and other design restrictions must also be placed in the Special Provision for Maintaining Traffic. | ||
| + | |||
| + | =====Example 3.4: Traffic Regulator===== | ||
| + | A seven mile milling and resurfacing construction project is scheduled on a two lane, two-way portion of M-44. Construction operations allow for traffic regulator control to maintain one lane, alternating during working hours, and two lanes open during non-working hours. The existing posted speed is 55 mph and the work zone will be signed for 45 mph. | ||
| + | |||
| + | Calculate the design hour volume (DHV) and delay for a traffic regulator set up. | ||
| + | |||
| + | =====Solution 3.4: Traffic Regulator===== | ||
| + | Traffic count information for this location can be found at [https://mdot.public.ms2soft.com/tcds/tsearch.asp?loc=Mdot&mod= MDOT TDMS]. The TDMS data indicates that the AADT is 5,950 vehicles for this segment. This traffic volume is cumulative of both directions of travel. If a breakdown of hourly traffic is available it must be used or the AADT number needs to be converted using the design hour volume (DHV) in vph. | ||
| + | |||
| + | Multiply the AADT by the DHV % to obtain the DHV. TDMS indicates that the DHV% for this segment is 12%: | ||
| + | |||
| + | ''(5,950 veh) × (12% DHV) = 714 vph'' | ||
| + | |||
| + | Use the table for Appendix H. Capacity in Traffic Regulator Zones to determine the maximum allowable length of the work zone given the 45 mph speed limit. The design hour has 714 vph. Utilizing the table for Appendix H. Capacity in Traffic Regulator Zones traffic regulation operation will result in delays of 10 minutes or less (714 is less than 725 which is capacity at 2.0 miles). Confirm hourly volume calculation with hourly traffic volumes if available. | ||
| + | |||
| + | The work zone length should be further evaluated using the [https://www.michigan.gov/mdot/Business/Construction/co-analysis CO3 Flagging] to confirm travel time delays do not exceed 10 minutes. The allowable length of the lane closure must be specified in the Traffic Restrictions in the Special Provision for Maintaining Traffic. | ||
| + | |||
| + | ==3.01.03 Temporary Traffic Signals== | ||
| + | Temporary traffic signals are often included in construction projects. They are categorized into two types, portable and fixed (pole mounted). | ||
| + | |||
| + | Portable signals may be necessary on projects when only one lane of traffic can be maintained at a time and traffic regulating operations are not recommended. On projects that extend over 30 days, the option of connecting to a power source is not required but should be considered. When a portable signal remains in place and all lanes are open, the signal should be removed or placed in yellow flash mode. | ||
| + | |||
| + | If possible, driveways or side streets within the temporary signal heads should be avoided. If unavoidable, contact the [https://www.michigan.gov/mdot/Business/work-zone-mobility WZDE] for potential solutions. | ||
| + | |||
| + | The [https://www.michigan.gov/mdot/programs/tsmo/maintenance Maintenance/Operations Services Section] should be contacted on projects that require a temporary pole mounted traffic signal. The Maintenance/Operations Services Section does not typically provide timing permits for temporary portable traffic signals, but may assist in finding a power source. | ||
| + | |||
| + | Signal time modifications should be considered during planning stages to improve the work zone traffic flow. Field reviews and adjustments during construction should be made as required to improve the traffic flow. Signal head location, timing, detection, and pedestrian volumes should all be considered when making modifications. | ||
| + | |||
| + | Signal timing for temporary traffic signals used to alternate traffic in a single lane consists of the following intervals: | ||
| + | * Green Interval - should be selected to match traffic demand | ||
| + | * All Red and Yellow Intervals - per direction, based on travel speed and distance between stop bars | ||
| + | * [https://mdotcf.state.mi.us/public/tands/Details_Web/electronic_traffic_control_device_guidelines.pdf Electronic Traffic Control Device Guidelines] should be utilized for additional information | ||
| + | |||
| + | The stop bars are typically 50 feet from the temporary signal heads. Adjustment in the field may be necessary to maintain adequate visibility. The duration of the ''All Red'' Interval (for each direction) can be computed using the following equation: <div style="text-align: center;"></br> | ||
| + | <big>'''''R = <sup>D</sup>∕<sub>(1.47 × S)</sub>'''''</big></div></br> | ||
| + | Where: | ||
| + | </br> | ||
| + | '''''R''''' = All Red Interval (sec) | ||
| + | </br> | ||
| + | '''''D''''' = Distance between stop bars (feet) | ||
| + | </br> | ||
| + | '''''S''''' = Speed limit through work zone (mph) | ||
| + | |||
| + | ==3.01.04 Interrupted Flow Facilities== | ||
| + | The travel time computation for interrupted flow facilities, such as two lane or multilane highways with stop controlled or signalized intersections, should be inclusive of speed delay, queue delay, and control delay. | ||
| + | |||
| + | The complexity of calculating control delay at intersections is magnified when intersection operations are changed within the work zone. This could include a reduction in the number of lanes available, or changes in the phasing of traffic signals. Software tools are recommended to determine travel time for interrupted flow facilities, due to their complexity. Software tools such as Synchro and SimTraffic provide a good estimation of travel time delay during construction. | ||
| + | |||
| + | ===A. Control Delay Signalized Intersections=== | ||
| + | The control delay can be estimated by using Synchro, SimTraffic, or manually using the methodology presented in the HCM for work zones with a single isolated signalized intersection. Control delay consists of two components: uniform delay, and incremental delay. | ||
| + | |||
| + | Control delay is computed using the following equation: | ||
| + | <div style="text-align: center;"></br> | ||
| + | <big>'''''d = d<sub>1</sub> + d<sub>2</sub>'''''</big></div></br> | ||
| + | Where: | ||
| + | </br> | ||
| + | '''''d<sub>1</sub>''''' = uniform delay (sec/veh) | ||
| + | </br> | ||
| + | '''''d<sub>2</sub>''''' = incremental delay (sec/veh) | ||
| + | </br> | ||
| + | Uniform delay accounts for arrival demand in the subject lane group that is uniformly distributed over time. | ||
| + | |||
| + | The uniform delay '''''d<sub>1</sub>''''' is computed using the following equation:<div style="text-align: center;"></br> | ||
| + | <big>''''' d<sub>1</sub> = <sup>0.5C[1 − ( <sup>g</sup>∕<sub>C</sub> )]<sup>2</sup></sup>∕<sub>1 − [min(1,X)( <sup>g</sup>∕<sub>C</sub> )]</sub>'''''</big> | ||
| + | </div></br> | ||
| + | Where: | ||
| + | </br> | ||
| + | '''''C''''' = cycle length (sec) | ||
| + | </br> | ||
| + | '''''g''''' = green time for analyzed phase (sec) | ||
| + | </br> | ||
| + | '''''X''''' = V/C ratio | ||
| + | </br> | ||
| + | The notation '''''min(1,X)''''' used in the equation indicates that the smaller of the two values is used. | ||
| + | |||
| + | Incremental delay accounts for random variation in arrivals and delay caused by demand exceeding capacity during the analysis period. The incremental delay '''''d<sub>2</sub>''''' is computed using the following equation: | ||
| + | <div style="text-align: center;"></br> | ||
| + | <big>'''''d<sub>2</sub> = 900T{(X − 1) + [(X − 1)<sup>2</sup> + <sup>4X</sup>∕<sub>cT</sub> )]<sup><sup>1</sup>∕<sub>2</sub></sup> }'''''</big> | ||
| + | </div></br> | ||
| + | Where: | ||
| + | </br> | ||
| + | '''''c''''' = lane group capacity (VPH) | ||
| + | </br> | ||
| + | '''''T''''' = analysis period duration (hr) | ||
| + | |||
| + | It should be noted that while the equation for incremental delay is purportedly valid for all values of '''''X''''', including highly oversaturated lane groups, enormous delays will be predicted for situations where '''''X''''' > 1.0 meaning demand exceeds capacity. Therefore, it is recommended that software tools are used to calculate control delay in situations when the computed '''''X''''' > 1.0. | ||
| + | |||
| + | The capacity value for the signalized lane group is necessary for both components of the control delay formula. Each lane group has a different capacity value, depending on the arrangement of turns permitted from the lane group. Capacity values may obtained from Table 3-3. | ||
| + | |||
| + | =====Example 3.5: Control Delay Signalized Intersection===== | ||
| + | A detour of M-20 will add 650 VPH as right turns to a signalized intersection with an existing traffic volume of 200 veh/hr. The lane group consists of a shared left-right-through lane. The signal will be timed for 60% green for the analyzed movement, and the cycle length will be 80 seconds. Calculate total control delay. | ||
| + | |||
| + | =====Solution 3.5: Control Delay Signalized Intersection===== | ||
| + | The lane group capacity is found from Table 3-4 based on 60% green time and unrestricted 12 feet lanes for 100% Turns. The estimated lane group capacity is 870 veh/hr. | ||
| + | |||
| + | The term for '''''<sup>g</sup>∕<sub>C</sub>''''' is already known to be 60% or 0.60. | ||
| + | |||
| + | The V/C ratio is calculated as: <div style="text-align: center;"></br> | ||
| + | <big>'''''X = <sup>850</sup>∕<sub>870</sub> = 0.98'''''</big></div></br> | ||
| + | The term for uniform delay '''''d<sub>1</sub>''''' is <div style="text-align: center;"></br> | ||
| + | <big>'''''d<sub>1</sub> = <sup>0.5 × 80(1 − 0.6)<sup>2</sup></sup>∕<sub>1 − [0.98 × 0.6]</sub> = 15.5 sec'''''</big></div></br> | ||
| + | The term for incremental delay '''''d<sub>2</sub>''''' is computed for the time interval for one hour, thus '''''T = 1''''' in the following equation: <div style="text-align: center;"></br> | ||
| + | <big>'''''d<sub>2</sub> = 900 × 1{(0.98 − 1) + [(0.98 − 1)<sup>2</sup> + ( <sup>4 × 0.98</sup>∕<sub>870 × 1</sub> )]<sup><sup>1</sup>∕<sub>2</sub></sup> } = 45 sec'''''</big></div></br> | ||
| + | The total control delay for this lane group is <div style="text-align: center;"></br> | ||
| + | <big>'''''d = 15.5 + 45 = 60.5 sec'''''</big></div> | ||
| + | |||
| + | ===B. Travel Time Determination=== | ||
| + | Similar to uninterrupted flow facilities, the initial travel time (before construction) should be computed or measured. Existing travel time runs may be completed to verify the existing conditions, especially to validate the existing travel time reported from software tools. The travel time estimates may be performed using various techniques summarized in [[Work Zone - 3.03 Mobility Analysis Tools#3.03.07 Travel Demand Models and Tools|Section 3.03.07 Travel Demand Models and Tools]]. | ||
| + | |||
| + | ==3.01.05 Detour Routes== | ||
| + | The determination of travel time delay for detour routes includes a comparison of the initial travel time on the original route (before construction) compared to the travel time during construction. The capacity conditions along the detour route will be important to consider, especially regarding the amount of traffic diverted to the detour route. If the detour route consists of traffic signals or other interrupted flow facilities, an evaluation of the intersection operations, including the detour traffic, may be necessary. | ||
| + | |||
| + | For detour routes with the necessary capacity to accommodate the diverted traffic volumes, the travel time along the detour route may be established as the travel distance divided by the average speed. A travel time run may be performed during the design development of the project to establish the anticipated detour travel time. Similarly, the detour travel time may be quickly determined using online map guidance tools, simply placing two points on a map, and routing the path along the detour route. | ||
| + | |||
| + | If intersection control delay is a particular concern for the detour route, the delay may be computed using software tools such as Synchro and added to the previously calculated detour travel time. This level of analysis should be completed when shutting off or detouring a major roadway movement, or the detour route is already at or above capacity, with existing traffic volumes. | ||
| + | |||
| + | ==Categories== | ||
| + | * [[Work Zone - Chapter 3 | Chapter 3: Mobility Analysis]] | ||
| + | * [[Work Zone - Index | Work Zone Safety and Mobility Manual Index]] | ||
Latest revision as of 12:53, 22 September 2022
3.01 Travel Time
The travel time delay should be estimated for the work zone to determine project significance as defined in Section 2.01 Project Significance. Consideration should be given to:
- Speed delay: Results from the reduced travel speed in the work zone, in comparison to the existing condition. This is affected by the temporary speed limit and by the capacity of the work zone.
- Queue delay: Additional time vehicles spend waiting in a queue. This is a result of the accumulation of vehicles upstream of a capacity reduction (i.e. a lane closure) when the demand exceeds the capacity.
- Control delay: Interruptions in traffic flow caused by temporary traffic control devices.
- Interruptions occur on all roadway types and include planned events (i.e. traffic regulators, temporary signals, temporary traffic stoppages).
Past experience should also be a factor when estimating travel times. Diversion rate of past projects in similar locations should be utilized to refine your estimation of work zone delay.
3.01.01 Uninterrupted Flow Facilities
Computing travel time for uninterrupted flow facilities (i.e. freeways or non-freeway without stop controlled or signal controlled intersections) consists of determining the speed delay and the queue delay.
A. Capacity Determination – Freeway
Table 3-1 Base Mainline Capacity and Table 3-2 Capacity Adjustment Factors should be used to estimate the capacity for each open lane. Apply factors known to adjust the base work zone capacity.
To begin the development of traffic control options, determine the number of lanes needed to handle the expected demand. An early check of available roadway capacity is critical as the vast majority of additional delay due to a work zone occurs when demand exceeds capacity for any appreciable length of time. The Highway Capacity Manual (HCM) Equation 10-9 can be used to determine the resulting adjusted capacity of the roadway lane:
Ca = {[(Cb + Ig + Iwt + Iwa ) × fhv × flw × fsc ] × N} − R
Where:
Ca = adjusted mainline capacity - vehicles per hour (vph)
Cb = base mainline capacity - vehicles per hour per lane (vphpl)
Ig = adjustment factor for geometrics (ranges from -150 to + 250 vphpl, could be zero). Select multiple factors that apply depending on the conditons; apply the cumulative adjustment factor.
Iwt = adjust factor for intensity of the work activity (ranges from -200 to +200 vphpl, could be zero). Select one factor
Iwa = adjustment factor for location of the work activity (ranges from -150 to +200 vphpl). Select one factor.
fhv = adjustment for heavy vehicles as defined in HCM Equation 10-8. Values have been provided for typical truck volume ranges
flw = adjustment for lane/shoulder widths
fsc = adjustment for lane/shoulder side clearance
N = number of lanes open through the work zone
R = manual adjustment for entrance ramps (vph)
The adjustment factor for work zone geometrics may be considered cumulatively. For example, work zone geometry when traffic uses a crossover and requires a traffic shift >3 feet would apply the cumulative effect of each condition as a part of the adjustment factor.
When determining the factors engineering judgement should be used to determine if the factors should be applied cumulatively. The base mainline capacity (Cb) and work zone capacity adjustment factors are provided in the tables below.
Table 3-1: Base Mainline Capacity
| Number of Lanes | Starting Capacity per Lane | |
|---|---|---|
| Normal | Open | Cb |
| 3 | 1 | 1400 |
| 2 | 1 | 1550 |
| 5 | 2 | 1600 |
| 4 | 2 | 1700 |
| 3 | 2 | 1700 |
| 4 | 3 | 1750 |
Table 3-2: Capacity Adjustment Factors
| Work Zone Conditions** | Capacity Adjustment Factors* | ||
|---|---|---|---|
| Geometry: traffic uses crossover | Ig | Subtract | 150 vphpl |
| Geometry: traffic driving on shoulder | Subtract | 150 vphpl | |
| Geometry: traffic shift (> 3 feet) | Subtract | 100 vphpl | |
| Geometry: work activity adjacent, protected with temporary barrier | Add | 250 vphpl | |
| Geometry: work activity adjacent (< 15 feet), protected by channelizing devices | Subtract | 100 vphpl | |
| Work Type: pavement repairs (concrete or HMA) | Iwt | Subtract | 200 vphpl |
| Work Type: rubblizing, reconstruction | Subtract | 150 vphpl | |
| Work Type: overhead activity (i.e. bridge work – painting, patching) | Subtract | 150 vphpl | |
| Work Type: cold milling, paving (concrete or HMA) | Subtract | 100 vphpl | |
| Work Type: guardrail or barrier | Add | 50 vphpl | |
| Work Type: signing installation | Add | 50 vphpl | |
| Work Type: occurs > 20 feet away | Add | 100 vphpl | |
| Work Activity: adjacent lane distance < 12 feet | Iwa | Subtract | 100 vphpl |
| Work Activity: adjacent lane distance > 12 feet, < 20 feet | Subtract | 50 vphpl | |
| Work Activity: adjacent lane distance > 20 feet away | Add | 150 vphpl | |
| Work Activity: separated by median | Add | 50 vphpl | |
| 12' lane width | flw | Multiply | 1.00 |
| 11' lane width | Multiply | 0.95 | |
| 10' lane width | Multiply | 0.90 | |
| Restricted one side | fsc | Multiply | 0.95 |
| Restricted both sides | Multiply | 0.90 | |
| Trucks 0% to ≤ 5% | fhv | Multiply | 1.00 |
| Trucks > 5% to ≤ 10% | Multiply | 0.98 | |
| Trucks > 10% to ≤ 15% | Multiply | 0.95 | |
| Trucks > 15% to ≤ 20% | Multiply | 0.93 | |
| Trucks > 20% | Multiply | 0.90 | |
| Entrance ramp within 1,500 feet downstream from the end of the lane closure taper | R | Subtract | Hourly ramp volume (max 600 vph) |
Example 3.1: Freeway
A construction project is planned for a two-lane freeway portion of US-127. The project will last for several months and involves complete reconstruction of the roadway and several bridges on each bound. One lane of traffic is proposed to be maintained in each direction by using temporary crossovers. Maintained traffic must drive on the shoulder. Lane widths will be reduced to 11 feet, with temporary concrete barrier separating opposing traffic. The traffic characteristics consist of 7% trucks. Calculate Lane capacity.
Solution 3.1: Freeway
The lane capacity is computed by starting with the base capacity (Cb) for a 2 lane freeway to a 1 lane freeway 1550 vphpl. The adjustment factor applied for geometry includes use of a crossover, with a > 3 foot shift, and traffic driving on the shoulder. Since we are only allowed to use one factor Ig = -100 (could range from 100 to 150). Although the work type is reconstruction, it is not in close proximity to the maintained traffic since it occurs on the closed bound of the freeway (Iwt = 100). The adjustment factors applied for work activity (Iwa = 50), lane width (flw = 0.95), side clearance (fsc = 0.95), and percent trucks (fhv = 0.98). The adjusted capacity is:
Ca = [(1550 − 100 + 100 + 50) × 0.95 × 0.95 × 0.98] = 1415 vph
Example 3.2: Freeway
A construction project is planned for an urban three lane freeway portion of I-696. The project will last a few months and involves replacement of median barrier and lighting fixtures. The median lane will be closed in each direction during some parts of the day using channelizing devices. The work activity is less than 12 feet from traffic. The traffic characteristics consist of 15% trucks. Calculate lane capacity.
Solution 3.2: Freeway
The lane capacity is computed by starting with the base capacity (Cb) for a 3 lane freeway to a 2 lane freeway 1700 vphpl. Adjustments are applied for close proximity intense work activity (Ig = -100), (Iwt = 50), (Iwa = -150), side clearance (fsc = 0.95), percentage trucks (fhv = 0.95). The adjusted capacity for two open lanes is:
Ca = {[(1700 − 100 + 50 − 100) × 0.95 × 0.95] × 2} = 2798 vph or 1399 vphpl
B. Traffic Demand Determination
An estimation of the hourly traffic demand is necessary to proceed with travel time delay and queue estimations. Existing traffic volume data is regularly collected on most state trunklines. Information regarding traffic data is provided in Section 2.03.01.A Traffic Information.
The level of detail of traffic volume data depends on the level of analysis. Hourly traffic volume data is necessary to accurately evaluate mobility impacts on facilities that may have fluctuations in traffic demand throughout the day. This is of particular importance if the temporary traffic control plan considers implementing traffic restrictions or lane closures only during certain portions of the day.
Weekend and weekday volumes are necessary when determining week day restrictions. Reviewing traffic volumes from the same time frame is important to make sure the traffic patterns are similar. This is amplified when dealing with an area that has a yearly traffic generator such as a school or seasonal traffic.
C. Speed Delay
The speed delay component of travel time delay is affected by the temporary speed limit and by the capacity conditions of the work zone. As a base line, the initial travel time (before construction work) should be computed or measured. Most roadways that operate at less than capacity, the initial travel time may be estimated by dividing the segment length by the existing posted speed limit. It should be recognized, however, in areas where recurring congestion is present, the existing travel time should be inclusive of recurring congestion due to near or at capacity operations.
Measured operating speed may be available on RITIS. Existing travel time runs should be completed to verify the existing conditions.
The proposed posted temporary speed limit should be considered the maximum operating speed during construction activities. It is important to consider the presence of special reduced speed limits in Michigan, such as the “45 MPH Where Workers Present” condition. The actual operating speed within a work zone may still be less than the posted work zone speed depending on the capacity conditions and worker location.
The relative nearness of the traffic demand to capacity is related using the V /C ratio. The V/C ratio may be used as a performance measure for the work zone operations.
The speed delay attributable to the work zone can be computed as the difference in the travel time during construction and before construction. The following formula may be used to compute speed delay:
t = D × ( 1∕Uwz − 1∕Ui ) × 60
Where:
t = speed delay (min)
D = work zone length, from reduce speed signing to return to existing roadway speed (miles)
Uwz = operating work zone speed (mph)
Ui = existing posted or operating speed before construction (mph)
D. Queue Delay
A queue is an accumulation of vehicles for each time period in which the arrivals, or demand, exceeds the departures, or capacity. The queue delay component of travel delay is estimated only when the demand exceeds capacity and a queue forms. When the demand traveling through the work zone is less than or equal to capacity, no queue is formed and no queue delay is encountered.
Spreadsheet tools or software are helpful in performing the computation of queue delay, since the accumulation and dissipation of queues may occur across multiple time periods. The delay encountered at a queue is estimated using the volume of vehicles accumulated in the queue and the capacity at which the queue is serviced.
The following formula can be used to compute the delay time for a vehicle at the back of the queue:
t = ( Q∕Ca ) × 60
Where:
t = queue delay (min)
Q = number of vehicles in queue (# of veh)
Ca = adjusted mainline capacity (vph)
Example 3.3: Urban Freeway, Queue Delay
Building from Example 3.2, the demand on this urban freeway is 3000 vph. The work zone is 5 miles long and the existing posted speed is 70 mph. During Construction the work zone will be signed for:
45 MPH
Where Workers Present.Calculate the queue delay.
Solution 3.3 Urban Freeway, Queue Delay
The adjusted mainline capacity estimated earlier is 2798 vph. The accumulated queue for the time period (hour) is the demand that exceeds the capacity.
The queue delay is:
Table 33: Per Lane Capacity for Signalized Flow
| Lane Characteristics | No Turns | 50% Turns* | 100% Turns* or Right-turn lane |
U-turn crossover | |||||
|---|---|---|---|---|---|---|---|---|---|
| Lane width (ft) | 12 | 10 | 12 | 10 | 12 | 10 | N/A | ||
| Green Time | 40% | Unrestricted | 620 | 550 | 560 | 500 | 520 | 450 | 530 |
| Restricted | 580 | 510 | 520 | 460 | 480 | 420 | 490 | ||
| 50% | Unrestricted | 850 | 750 | 770 | 680 | 710 | 620 | 670 | |
| Restricted | 800 | 700 | 730 | 640 | 670 | 590 | 630 | ||
| 60% | Unrestricted | 1040 | 910 | 940 | 830 | 870 | 760 | 810 | |
| Restricted | 970 | 850 | 880 | 780 | 810 | 710 | 760 | ||
3.01.02 Traffic Regulator Operation
(Updated 12/3/2020) Traffic regulator operations, on the mainline traffic with alternating flow, should be evaluated based on travel time delay. The travel time delay calculation is determined using the Construction, Congestion, Cost Software (CO3) Flag Spreadsheet. The capacity of a traffic regulator operation is directly related to the posted work zone speed, volume of traffic, and the length of the traffic regulator zone.
The chart and graphs provided in Appendix B: Mobility Analysis Tools present capacity during traffic regulating on two-lane roadways. Once this determination is made, it can be used in the CO3 analysis to evaluate the travel time delay associated with work zone lengths. The value, as determined by the chart and the CO3 analysis, should be specified in the TMP. The length of the work zone and other design restrictions must also be placed in the Special Provision for Maintaining Traffic.
Example 3.4: Traffic Regulator
A seven mile milling and resurfacing construction project is scheduled on a two lane, two-way portion of M-44. Construction operations allow for traffic regulator control to maintain one lane, alternating during working hours, and two lanes open during non-working hours. The existing posted speed is 55 mph and the work zone will be signed for 45 mph.
Calculate the design hour volume (DHV) and delay for a traffic regulator set up.
Solution 3.4: Traffic Regulator
Traffic count information for this location can be found at MDOT TDMS. The TDMS data indicates that the AADT is 5,950 vehicles for this segment. This traffic volume is cumulative of both directions of travel. If a breakdown of hourly traffic is available it must be used or the AADT number needs to be converted using the design hour volume (DHV) in vph.
Multiply the AADT by the DHV % to obtain the DHV. TDMS indicates that the DHV% for this segment is 12%:
(5,950 veh) × (12% DHV) = 714 vph
Use the table for Appendix H. Capacity in Traffic Regulator Zones to determine the maximum allowable length of the work zone given the 45 mph speed limit. The design hour has 714 vph. Utilizing the table for Appendix H. Capacity in Traffic Regulator Zones traffic regulation operation will result in delays of 10 minutes or less (714 is less than 725 which is capacity at 2.0 miles). Confirm hourly volume calculation with hourly traffic volumes if available.
The work zone length should be further evaluated using the CO3 Flagging to confirm travel time delays do not exceed 10 minutes. The allowable length of the lane closure must be specified in the Traffic Restrictions in the Special Provision for Maintaining Traffic.
3.01.03 Temporary Traffic Signals
Temporary traffic signals are often included in construction projects. They are categorized into two types, portable and fixed (pole mounted).
Portable signals may be necessary on projects when only one lane of traffic can be maintained at a time and traffic regulating operations are not recommended. On projects that extend over 30 days, the option of connecting to a power source is not required but should be considered. When a portable signal remains in place and all lanes are open, the signal should be removed or placed in yellow flash mode.
If possible, driveways or side streets within the temporary signal heads should be avoided. If unavoidable, contact the WZDE for potential solutions.
The Maintenance/Operations Services Section should be contacted on projects that require a temporary pole mounted traffic signal. The Maintenance/Operations Services Section does not typically provide timing permits for temporary portable traffic signals, but may assist in finding a power source.
Signal time modifications should be considered during planning stages to improve the work zone traffic flow. Field reviews and adjustments during construction should be made as required to improve the traffic flow. Signal head location, timing, detection, and pedestrian volumes should all be considered when making modifications.
Signal timing for temporary traffic signals used to alternate traffic in a single lane consists of the following intervals:
- Green Interval - should be selected to match traffic demand
- All Red and Yellow Intervals - per direction, based on travel speed and distance between stop bars
- Electronic Traffic Control Device Guidelines should be utilized for additional information
The stop bars are typically 50 feet from the temporary signal heads. Adjustment in the field may be necessary to maintain adequate visibility. The duration of the All Red Interval (for each direction) can be computed using the following equation:
R = D∕(1.47 × S)
Where:
R = All Red Interval (sec)
D = Distance between stop bars (feet)
S = Speed limit through work zone (mph)
3.01.04 Interrupted Flow Facilities
The travel time computation for interrupted flow facilities, such as two lane or multilane highways with stop controlled or signalized intersections, should be inclusive of speed delay, queue delay, and control delay.
The complexity of calculating control delay at intersections is magnified when intersection operations are changed within the work zone. This could include a reduction in the number of lanes available, or changes in the phasing of traffic signals. Software tools are recommended to determine travel time for interrupted flow facilities, due to their complexity. Software tools such as Synchro and SimTraffic provide a good estimation of travel time delay during construction.
A. Control Delay Signalized Intersections
The control delay can be estimated by using Synchro, SimTraffic, or manually using the methodology presented in the HCM for work zones with a single isolated signalized intersection. Control delay consists of two components: uniform delay, and incremental delay.
Control delay is computed using the following equation:
d = d1 + d2
Where:
d1 = uniform delay (sec/veh)
d2 = incremental delay (sec/veh)
Uniform delay accounts for arrival demand in the subject lane group that is uniformly distributed over time.
The uniform delay d1 is computed using the following equation:
d1 = 0.5C[1 − ( g∕C )]2∕1 − [min(1,X)( g∕C )]
Where:
C = cycle length (sec)
g = green time for analyzed phase (sec)
X = V/C ratio
The notation min(1,X) used in the equation indicates that the smaller of the two values is used.
Incremental delay accounts for random variation in arrivals and delay caused by demand exceeding capacity during the analysis period. The incremental delay d2 is computed using the following equation:
d2 = 900T{(X − 1) + [(X − 1)2 + 4X∕cT )]1∕2 }
Where:
c = lane group capacity (VPH)
T = analysis period duration (hr)
It should be noted that while the equation for incremental delay is purportedly valid for all values of X, including highly oversaturated lane groups, enormous delays will be predicted for situations where X > 1.0 meaning demand exceeds capacity. Therefore, it is recommended that software tools are used to calculate control delay in situations when the computed X > 1.0.
The capacity value for the signalized lane group is necessary for both components of the control delay formula. Each lane group has a different capacity value, depending on the arrangement of turns permitted from the lane group. Capacity values may obtained from Table 3-3.
Example 3.5: Control Delay Signalized Intersection
A detour of M-20 will add 650 VPH as right turns to a signalized intersection with an existing traffic volume of 200 veh/hr. The lane group consists of a shared left-right-through lane. The signal will be timed for 60% green for the analyzed movement, and the cycle length will be 80 seconds. Calculate total control delay.
Solution 3.5: Control Delay Signalized Intersection
The lane group capacity is found from Table 3-4 based on 60% green time and unrestricted 12 feet lanes for 100% Turns. The estimated lane group capacity is 870 veh/hr.
The term for g∕C is already known to be 60% or 0.60.
The V/C ratio is calculated as:
X = 850∕870 = 0.98
The term for uniform delay d1 is
d1 = 0.5 × 80(1 − 0.6)2∕1 − [0.98 × 0.6] = 15.5 sec
The term for incremental delay d2 is computed for the time interval for one hour, thus T = 1 in the following equation:
d2 = 900 × 1{(0.98 − 1) + [(0.98 − 1)2 + ( 4 × 0.98∕870 × 1 )]1∕2 } = 45 sec
The total control delay for this lane group is
d = 15.5 + 45 = 60.5 sec
B. Travel Time Determination
Similar to uninterrupted flow facilities, the initial travel time (before construction) should be computed or measured. Existing travel time runs may be completed to verify the existing conditions, especially to validate the existing travel time reported from software tools. The travel time estimates may be performed using various techniques summarized in Section 3.03.07 Travel Demand Models and Tools.
3.01.05 Detour Routes
The determination of travel time delay for detour routes includes a comparison of the initial travel time on the original route (before construction) compared to the travel time during construction. The capacity conditions along the detour route will be important to consider, especially regarding the amount of traffic diverted to the detour route. If the detour route consists of traffic signals or other interrupted flow facilities, an evaluation of the intersection operations, including the detour traffic, may be necessary.
For detour routes with the necessary capacity to accommodate the diverted traffic volumes, the travel time along the detour route may be established as the travel distance divided by the average speed. A travel time run may be performed during the design development of the project to establish the anticipated detour travel time. Similarly, the detour travel time may be quickly determined using online map guidance tools, simply placing two points on a map, and routing the path along the detour route.
If intersection control delay is a particular concern for the detour route, the delay may be computed using software tools such as Synchro and added to the previously calculated detour travel time. This level of analysis should be completed when shutting off or detouring a major roadway movement, or the detour route is already at or above capacity, with existing traffic volumes.